| Facility wide emission calculations | Calculations | SEP-06-2024 |
| Source 01,02, 21 MMBtu/hr natural gas-fired boiler, Storage tanks | Permit | SEP-06-2024 |
| Emission summary | Emission Summary | SEP-06-2024 |
| Facility feedback on draft permit and request to set PM and SO2 emissions to allowable limit per regulations | Email | AUG-23-2024 |
| Insignificant activity determination letter for Source 05 | Letter | AUG-07-2024 |
| Source 00, Asphalt Paving Mixtures and Blocks | Public Notice Document | JUL-25-2024 |
| Source 00, Asphalt Paving Mixtures and Blocks | Public Notice Document | JUL-25-2024 |
| Email confirming no changes to tank contents from 2014 and additional info on boiler | Email | JUN-17-2024 |
| Source 00, Asphalt Paving Mixtures and Blocks | Application | MAY-16-2024 |
| Certified Mail Receipt | Certified Mail Receipt | MAY-15-2024 |
| Source 00 - Asphalt Paving Mixtures and Blocks | Application | MAY-10-2024 |
| Letter requesting updated/additional information | Letter | MAY-09-2024 |
| Source 00 - Asphalt Paving Mixtures and Blocks - Intentional Backlog Notification | Email | FEB-26-2024 |
| Source 00 - Asphalt Paving Mixtures and Blocks | Application | FEB-02-2024 |
| Old Application with Storage Tank Calcs | Old Application | MAR-01-2014 |