Skip to Main Content
  • Site Information

SITE INFORMATION

Memphis Regional Megasite
Jackson
Haywood
The Project consists of the realignment of approximately 1,700 feet of Fredonia Road south of the intersection with Keeling Road, north of Interstate 40 and south of State Route 79, southeast of the Town of Stanton within Haywood County, Tennessee.
101 Fredonia Loop
Stanton
38069

Site Map

DWR Permits at this Site

NR1302.075State of Tennessee - Department of General Services (DGS)Wastewater force main and on-site water distribution system - Memphis Regional MegasiteARAPWithdrawn - -
NRS08.260Haywood County - ARAPWithdrawn - -
NRS13.248State of Tennessee - Department of General Services (DGS)Memphis Regional Megasite - Utility Crossing – Multiple Streams and WetlandsARAPWithdrawn - -
NRS17.054State of Tennessee - Department of General Services (DGS)Memphis Megasite - Installation of 18 inch HDPE Force Main to the Mississippi RiverARAPInactive5/1/20184/30/2023
NRS18.287State of Tennessee - Department of General Services (DGS)Memphis Regional Megasite Force Main 3ARAPInactive - -
NRS21.238Ford Motor CompanyBlue Oval CityARAPActive3/22/20223/21/2027
NRS22.127Memphis Regional Megasite AuthorityMemphis Regional Megasite, Site Water Piping and Sanitary Sewer Force MainARAPInactive9/29/20229/28/2027
NRS23.159Tennessee Department of Transportation (TDOT)PIN 132709.00, PE #R4S222-S1-002ARAPActive10/16/202310/15/2028
NRS23.237Tennessee Department of Transportation (TDOT)24S222-S1-003; PIN 132132.04 (Project Blue Oval)ARAPActive4/23/20244/22/2029
NRS24.151Becknell Services, LLCFredonia Road Improvement ProjectARAPComplete - -

Documents at this Site

View
TN0082368Email12/13/24 Response from Ford regarding complaint #13449912/13/2024
TN0082368LetterTN0082368 Email chain with response from Ford per 11/1/24 letter with associated attachments12/6/2024
NRS24.151LetterApplicant Letter of Responsibility 11/26/2024
NRS24.151Draft PermitDraft Permit11/26/2024
NRS24.151Public Notice DocumentPublic Notice Document11/26/2024
NRS24.151EmailPublic Notice Email11/26/2024
NRS24.151AddendumRevised debit calculation11/25/2024
TN0082368LetterTN082368 Ford response to TDEC's 11/1/24 letter11/22/2024
TN0082368LetterTN0082368 Signatory Authority Letter regarding site inspections being delegated to Blake Newbill.11/22/2024
NRS24.151LetterMitigation bank preliminary credit reservation letter11/19/2024
TN0082368LetterTN0082368 Follow-up letter to July 19 2024 CEI11/1/2024
NRS24.151AddendumRevised SQT Data10/15/2024
NRS24.151AddendumRAI Response and Revised SQT Data10/15/2024
-LetterTemporary Water Plant Approval12/8/2023
-Emailemail with spill response report11/21/2023
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Complaints on this Site

View
See Details11/20/2024Stormwater - ConstructionIssue Resolved
See Details9/26/2023Pollution / Spills / Illicit DischargeIssue Resolved
See Details7/7/2023Stormwater - ConstructionReferred to other Agency
See Details5/26/2011OtherClosed

Inspections at this Site

Permittee Name
05-DEC-2023- - Construction Inspection - Site 1In Compliance
12-AUG-2009- - Reconnaissance (RI)In Compliance