| TN0059366 | Report | Mosheim TRE Report Dated August 26, 2024 | 8/29/2024 |
| TN0059366 | Addendum | December 12-18 2023 Biomonitoring Report Attachment to Mosheim TRE Report dated August 26, 2024 | 8/29/2024 |
| TN0059366 | Addendum | March 5-11 2024 Biomonitoring Report Attachment to Mosheim TRE Report dated August 26, 2024 | 8/29/2024 |
| TN0059366 | Addendum | May 7-14 Biomonitoring Report Attachment to Mosheim TRE Report dated August 26, 2024 | 8/29/2024 |
| TN0059366 | Addendum | May 21-27 Biomonitoring Report Attachment to Mosheim TRE Report dated August 26, 2024 | 8/29/2024 |
| TN0059366 | Addendum | 06_18_2024 Biomonitoring TIE Report Attachment to Mosheim TRE Report dated August 26, 2024 | 8/29/2024 |
| TN0059366 | Notice of Violation | NOV for effluent violations on EPA's QNCR from May to July 2024, 2 consecutive WET failures in May and June 2024, and requirement to initiate TIE/TRE | 8/22/2024 |
| TN0059366 | Letter | SENT VIA EMAIL 08_22_2024
Letter of Advisement Concerning
Complaint Received 08_08_2024 | 8/22/2024 |
| TN0059366 | Monitoring Report | Lick Creek Valley WWTP July 2024 MOR | 8/16/2024 |
| TN0059366 | Letter | RCVD VIA EMAIL 08_13_2024
Response to Additional Question Regarding
Response to Pretreatment Audit NOV performed on March 19, 2024 | 8/13/2024 |
| TN0059366 | Letter | Response to PT NOV dated 26-APR-24 | 8/13/2024 |
| TN0059366 | Letter | WPN24.0300 Approval Letter 20240809 | 8/9/2024 |
| TN0059366 | Letter | RCVD 26-JUL-24: letter re: Lick Creek Valley Waste Water Treatment Plant has been violating the CWA and NEPA for 4 years by Park Overall | 7/26/2024 |
| TN0059366 | Notice of Violation | SENT VIA EMAIL 07_18_2024
Notice of Violation Related to Complaint
Investigation on 07_02_2024 | 7/18/2024 |
| TN0059366 | Corrective Action Plan | RCVD VIA EMAIL 07_17_2024
Response to NOV sent April 26, 2024