View | | | | |
| TNR192155 | Notice of Termination | RCVD VIA EMAIL 26-NOV-24: NOT removing contractor, by Richard Crowe | 11/26/2024 |
| TN0082228 | Report | TN0082228 TVA October 2024 Monthly Summary Report | 11/13/2024 |
| TN0082228 | Letter | TVA is currently reviewing permitting options and requests an extension for the application submittal to March 2, 2025. (granted by Email from Vojin Janjic dated 11/1/2024) | 11/1/2024 |
| TNR053184 | Monitoring Report | TNR053184 2024 Annual Storm Water Monitoring Report Outfall F04, F05, F06, F07, F08, and F09 | 10/25/2024 |
| TN0082228 | Letter | TN0082228 TVA September 2024 Monthly Summary Report | 10/16/2024 |
| TNR192155 | Notice of Coverage (NOC) | Notice of Coverage (NOC) October 2024 | 10/1/2024 |
| TNR192155 | Notice of Intent (NOI) | TNR192155 - SWPPP modification and updated NOI request | 9/30/2024 |
| TN0082228 | Letter | TN0082228 TVA August 2024 Monthly Summary Report | 9/17/2024 |
| TN0082228 | Letter | TN0082228 TVA July 2024 Monthly Summary Report | 8/15/2024 |
| TN0005355 | Letter | Delegation of signatory authority
General Manager Gas Operations, Regional
Gas Operations Senior Managers, Plant
Manager Integrated CC and CT Site, and
Operations Managers | 8/15/2024 |
| TN0082228 | Letter | TN0082228 TVA June 2024 Monthly Summary Report | 7/12/2024 |
| TNR192266 | Notice of Termination | NOTs for the subject construction general permit. The demolition of the ACT
combustion turbines and restoration of the site has achieved final stabilization | 7/12/2024 |
| TNR192155 | Notice of Termination | contractor NOT from Brandenburg Industrial Service Company | 7/10/2024 |
| TN0082228 | Letter | TN0082228 TVA May 2024 Monthly Summary Report | 6/12/2024 |
| TNR191994 | Letter | Annual Maintenance Fee Notice Letter | 5/23/2024 |
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.