Atmos Energy Union City North Transmission Pipeline Replacement Project
Jackson
Obion
Union City North 4" Gas Pipeline Replacement with 8" pipeline in 5-mile x 100' corridor with multiple stream and wetland crossings using HDD
Hollie Hutchison Road, approximately one-mile southwest of the intersection of Hollie Hutchison Road and Old Fulton Harris Road, to its eastern terminus along Wolf Creek Road
Union City
38261

Site Map

DWR Permits at this Site

NR2302.037Atmos Energy CorporationUnion City North Gas Pipeline ReplacementARAPActive8/9/20238/9/2024
NRS24.029Atmos Energy CorporationUnion City North Gas Pipeline ReplacementARAPIncomplete - -
TNR122932Atmos Energy Corporation - CGPPending - -

Documents at this Site

View
NRS24.029Emailrequest for additional information8/27/2024
TNR122932Notice of Intent (NOI)SWPPP8/8/2024
NRS24.029AddendumARAP Payment3/18/2024
NRS24.029ApplicationApplication Package3/13/2024
NRS24.029EmailAcknowledgment of Application Intent Email2/23/2024
NRS24.029LetterAcknowledgment of Application Intent2/23/2024
NRS24.029LetterLetter to Atmos Energy stating IP is required for more than 1 ac. or temporary wetland impacts in Wetland 12/6/2024
NR2302.037Letterletter to Atmos Energy stating IP is required for more than 1 ac. or temporary wetland impacts in Wetland 12/6/2024
NR2302.037Emailemail from Kaitlin Illick, RES Environmental regarding modification to HDD with my response1/9/2024
NR2302.037Applicationcopy of fee receipt8/9/2023
NR2302.037Notice of Coverage (NOC)NOC signed8/9/2023
NR2302.037Applicationcontinuation of ARAP app8/7/2023
NR2302.037ApplicationARAP app8/7/2023