Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO Name
169148Reunion at TownshipLEBANON RDMOUNT JULIETWilsonNashville

Permit Information

NR2304.032
ARAP
Construction and Removal of Minor Road Crossings
Active
MidSouth Multifamily Group LLC
Madison at Township
Road Crossing for Phase 1. The permanent road crossing proposes the installation of 36 linear feet 18’x6’ slab bridge under the proposed road to allow the stream to remain in its existing condition. The slab bridge will be set, and fill material will be placed above it.
N/A
05-JAN-2024
26-JAN-2023
02-FEB-2024
02-FEB-2024
07-APR-2025
Spencer Creek
01-JUL-2024 04:13PM

Other DWR permits at this site

  • 1 - 5 of 5
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
NR2304.033MidSouth Multifamily Group LLCMadison at Township ARAPActiveN/ANashville-02-FEB-202407-APR-2025
TNR245833MidSouth Multifamily Group, LLCReunion at TownshipCGPActiveN/ANashville-06-MAY-202230-SEP-2026
NR2204.060MidSouth Multifamily Group, LLCReunion at Township (Utility Crossing)ARAPActiveN/ANashville-06-MAY-202207-APR-2025
NR2204.059MidSouth Multifamily Group, LLCReunion at Township (Road Crossing)ARAPActiveN/ANashville-06-MAY-202207-APR-2025
TNR246559Midsouth Multifamily Group, LLCMadison at TownshipCGPActiveN/ANashville-08-APR-2024-
  • 1 - 5 of 5

Permit Documents

View
Notice of Coverage (NOC)Notice of Coverage (NOC) 202401-JUL-2024
EmailIncomplete ARAP Response 05-JAN-2024
EmailIncomplete ARAP Notification- TWRA Coordination required 27-FEB-2023
ImageFee Paid27-JAN-2023
ApplicationARAP26-JAN-2023
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections

no data found