Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO Name
2113Town of Puryear300 Highway 140 EastPuryearHenryJackson

Permit Information

SOP-89067
SOP
Reissuance
Town of Puryear
Town of Puryear Wastewater Treatment Facility
Sewage collection system, lagoon and spray irrigation
N/A
M
SI
13-AUG-2024
04-SEP-2024
26-SEP-2024
01-OCT-2024
01-JUL-2018
01-AUG-2018
31-JUL-2023
Unnamed Tributary to East Fork Clarks River - no discharge
treated domestic wastewater; no discharge allowed
Sewage collection system, lagoon and spray irrigation
.08
01-OCT-2024 07:45AM

Other DWR permits at this site

No other permits found.

Permit Documents

View
Topo MapREF 01-JAN-89: schematics for plant and lagoon from Town of Puryear01-JAN-1989
ApplicationRCVD 12-SEP-12: SOP app by Rickie Hughes.12-SEP-2012
PermitSOP Permit (2013)03-JUN-2013
Environmental ReviewPuryear CEI Letter, 3560 and inspection form09-SEP-2014
ApplicationRCVD 15-NOV-17: SOP app by Rickie Hughes.15-NOV-2017
ApplicationRCVD 17-APR-18: part of SOP app re: ck# 8877 for $1000 by David Varner.17-APR-2018
LetterComplete Application Letter26-APR-2018
Draft PermitDraft Permit03-MAY-2018
PermitFinal Permit27-JUN-2018
Inspection ReportPuyear CEI letter03-APR-2019
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

no data found

Inspections

13-MAY-2008Compliance Eval (non-sampling) (CEI)In Compliance
29-AUG-2014Compliance Eval (non-sampling) (CEI)In Compliance
30-JUN-2015Sanitary Sewer Overflow Non-SamplingReferred to Local Authority
26-MAR-2019Sanitary Sewer SystemIn Compliance
26-MAR-2019Compliance Evaluations (non-NPDES)In Compliance
20-MAR-2024Compliance Evaluations (non-NPDES)Out of Compliance

Wastewater Engineering Plans Review

23.0522ApprovedERRGO9/14/20239/20/2023Spray Field Center Pivot Installation
15.0152ApprovedSTPMODMNU4/8/20155/6/2015WWTP Improvements