Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO Name
5749Munford Sewer Department Lagoon1397 Munford Ave.MunfordTiptonMemphis

Permit Information

TN0062499
Individual
Modification
City of Munford
Munford Sewer Department Lagoon
Treatment of municipal sewage; Modification adds limits for a proposed expansion of the lagoon from 2.0 MGD to 3.0 MGD. Munford has determined that an increase in 1.0 MGD will be less than de minimis degradation of the river because of the river's size; The upgrade may warrant replacement of the outfall line.
M
M
MW
01-APR-2024
25-MAR-2024
17-MAY-2024
02-JUL-2024
14-AUG-2024
01-SEP-2024
31-DEC-2025
14-AUG-2024
Mississippi River at mile 761
treated municipal wastewater from Outfall 001 from a lagoon with chlorine disinfecting serving Munford and the Towns of Atoka and Brighton
lagoon system (exempt from 503)
4952
2
22-AUG-2024 07:32AM

Other DWR permits at this site

  • 1 - 2 of 2
  • 1 - 2 of 2

Permit Documents

View
Emailemail to Russell Norville17-SEP-2019
LetterWPN23.0493 ARP Memo 2023121111-DEC-2023
LetterWPN23.0449 Approval Letter 2023112121-NOV-2023
LetterWPN22.0083 SRF Memo 2022022424-FEB-2022
LetterWPN21.0695 ER letter 14-JUL-2021
LetterWPN17 0764 Approval20-NOV-2017
LetterWPN 18.0094R Extension Letter 03.05.202405-MAR-2024
ApplicationUpdated Application23-SEP-2020
ReportToxicity Study17-JUL-2019
LetterThe city is requesting that modified permit extends the expiration date until Decemebr 31, 202921-AUG-2024
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections

24-OCT-2022Performance Audit (PAI)In Compliance
03-OCT-2022Sanitary Sewer SystemIn Compliance
13-NOV-2020Compliance Eval (non-sampling) (CEI)In Compliance
23-MAY-2019Compliance Eval (non-sampling) (CEI)In Compliance
01-FEB-2017Compliance Eval (non-sampling) (CEI)In Compliance
01-FEB-2017Sanitary Sewer Overflow Non-SamplingIn Compliance
11-MAR-2015Compliance Eval (non-sampling) (CEI)In Compliance
06-FEB-2013Compliance Eval (non-sampling) (CEI)In Compliance
08-MAR-2011Compliance Eval (non-sampling) (CEI)In Compliance
27-APR-2009Compliance Eval (non-sampling) (CEI)In Compliance

Wastewater Engineering Plans Review

23.0493Review CompletePERTNH9/1/202312/11/2023Wastewater Treatment Expansion
23.0449ApprovedCDTNH10/25/202311/21/2023Bell Park Subdivision
18.0094RApprovedCDMJB6/9/20236/20/2023Villages of Green Meadows Phase 3
22.0328ApprovedCDA. Bahour8/22/20228/31/2022Villages of Green Meadows Subdivision 4A
21.0647ApprovedCDMNU11/9/202111/9/2021Walker Meadows North
21.0695Review CompleteCDTNH9/27/202110/8/2021SRF Munford Lagoon Influent Pump Upgrade
21.0382ApprovedCDMNU5/12/20216/7/2021Glenview Estates Section D
21.0215Review CompletePPDTNH3/11/20213/25/2021Munford Lagoon Upgrade
19.0562ApprovedCDA. Bahour11/8/201911/18/2019Walker Meadows Subdivision - Phase 2
17.0683RApproved-MNU2/19/20193/4/2019Walkers Meadows S/D