Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO Name
2266White House Utility District Collection System3303 Hwy 31WWhite HouseSumnerNashville

Permit Information

SOP-97022
SOP
Reissuance
White House Utility District
White House Collection System
Collection system to either Gallatin STP or Hendersonville collection system to Nashville Dry Creek STP
N/A
M
CS
08-JUN-2022
08-JUN-2022
15-NOV-2022
16-DEC-2022
01-FEB-2023
31-JAN-2028
31-JUL-2000
NA. Cumberland River is 0.59 miles away.
No discharge allowed
Sewage collection system to either Gallatin STP or Hendersonville collection system to Nashville Dry Creek STP
.01
30-MAY-2024 08:19AM

Other DWR permits at this site

No other permits found.

Permit Documents

View
LetterWPN24.0540 Approval Letter 2024081519-AUG-2024
Letter24.0024 Approval letter 2024042525-APR-2024
Letteravailable daily flows for permit.17-APR-2024
Letter24.0235 Plans Approval LTR 2024041616-APR-2024
LetterWPN24.0034 Approval Letter 2024031415-MAR-2024
LetterWPN24.0035 Approval Letter 2024021212-FEB-2024
Letter24.0024 Utility Approval letter08-JAN-2024
Letter23.0714 Approval letter14-DEC-2023
Letter20.0826 Extension Letter 09.13.202313-SEP-2023
Letter23.0155 TDEC Plans Approval Letter27-APR-2023
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

no data found

Inspections

08-FEB-2018Compliance Evaluations (non-NPDES)In Compliance
07-MAR-2008Compliance Evaluations (non-NPDES)In Compliance

Wastewater Engineering Plans Review

06.1550ApprovedSTDSPECA. Bahour11/16/200612/8/2006Standard Specifications
13.0627ApprovedLINEA. Bahour10/14/201311/8/2013Somerset Downs - Phase 4
14.0082ApprovedSTDSPECA. Bahour2/4/20142/18/2014White House Utility District Wastewater Standard Specifications
14.0068ApprovedLINEA. Bahour1/30/20142/24/2014Creekside at Station Camp Phase 6B
14.0069ApprovedLINEA. Bahour1/30/20142/25/2014Creekside at Station Camp Phase 6C
14.0138ApprovedLINEA. Bahour3/10/20144/25/2014Somerset Downs, Phase 5
14.0001ApprovedLPCSA. Bahour1/2/20144/30/2014Crutcher Station, Phase 1 Section 1 (Revised)
14.0236ApprovedLINEA. Bahour4/29/20145/29/2014Foxland Phase 7 Section 2
14.0227ApprovedLINEMNU4/22/20146/12/2014Saint Blaise Retreat Phase 2
14.0433ApprovedLPCSA. Bahour7/7/20148/7/2014Albatross Way