Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO Name
5207Clinton WWTP #1799 Melton Hill DrClintonAndersonKnoxville

Permit Information

TN0026506
Individual
Reissuance
Clinton Utilities Board
Clinton WWTP #1
Treatment of municipal sewage
M
M
MW
31-OCT-2022
15-NOV-2022
04-APR-2023
08-MAY-2023
01-JUN-2023
31-MAY-2028
Clinch River Mile 56.9
treated municipal wastewater from Outfall 001
Activated sludge and trickling filter processes preceded by primary clarification and followed by secondary clarification, chlorination and dechlorination. Sludge is aerobically digested and dewatered via vacuum filtration for landfill disposal.
4952
3
08-JUL-2024 03:41PM

Other DWR permits at this site

Permit Documents

View
ApplicationRCVD 31-OCT-22: NPDES app by Greg Jones.31-OCT-2022
ApplicationRCVD VIA EMAIL 13-OCT-17: NPDES app by Dan Hawkins.13-OCT-2017
ApplicationRCVD 22-OCT-12: NPDES app by Gregory Fay.22-OCT-2012
Draft Permitdraft permit 202304-APR-2023
Draft PermitDraft Permit06-FEB-2018
EmailPT Narrative Conditions Reminder24-JUL-2023
EmailNetDMR Final Approval15-SEP-2016
Engineering Drawings-PlansWPN15-0779 Construction Plans18-DEC-2015
Engineering Report17.0714 FastTrack PER; J D Yarnell Industrial Park Sewer Study; Clinton UB17-OCT-2017
Environmental Review20.0134 Anderson Higher Education Environmental Review17-APR-2020
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections

03-JUL-2024Compliance Eval (non-sampling) (CEI)In Compliance
10-MAY-2024Pretreatment Compliance (oversight)In Compliance
19-APR-2023Pretreatment TAV and File ReviewIn Compliance
12-JUL-2022Compliance Eval (non-sampling) (CEI)In Compliance
22-APR-2022Pretreatment Compliance (oversight)In Compliance
29-APR-2021Pretreatment AuditIn Compliance
30-NOV-2020Compliance Eval (non-sampling) (CEI)In Compliance
11-FEB-2020Pretreatment TAV and File ReviewIn Compliance
29-APR-2019Pretreatment Compliance (oversight)In Compliance
21-DEC-2018Compliance Eval (non-sampling) (CEI)In Compliance

Wastewater Engineering Plans Review

13.0640InactiveLINEA. Bahour10/23/2013-Summer Place
13.0779ApprovedIMPMNU12/30/20132/4/2014WWTP Aeration System Improvements
14.0083ApprovedLINEA. Bahour2/6/20144/23/2014Anderson Hall Apartments
14.0196ApprovedSTDSPECA. Bahour4/11/20144/22/2014Standard Specifications for Construction of Water and Sewer Utilities
15.0273ApprovedLINEA. Bahour6/1/20156/2/2015Derek Roesner Sewer Extension
16.1004ApprovedLINEMNU12/29/20161/25/2017Ridge View Drive
17.0435ApprovedPSMNU6/26/20177/17/2017Pump Station No 22 Renovation
17.0598ApprovedotherJim McAdoo9/12/20179/19/2017WWTP Clarifier Repurposing
17.0714ApprovedPERWDM10/17/201710/23/2017J D Yarnell Industrial Park
17.0846ApprovedLINEMNU12/18/20171/11/2018Crestwood Drive