Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO NameGIS
6470Tosh Farms - Huntland BGF587 Hog Haven LnHuntlandFranklinColumbiaView Map

Permit Information

TN0077755
CAFO-Individual
Pending
When initially received, all applications are identified as "Pending." Pending status indicates that the application is in the que to be processed or that TDEC-DWR staff are reviewing the application (or Notice of Intent for general permits). Status "Pending" could be also interpreted as "work in progress."
Tosh Farms - Huntland BGF
Eight barn farrow to wean hog operation w/ 11,339 total head capacity.
I
R
18-DEC-2024
11-JAN-2018
18-DEC-2024
06-FEB-2018
02-APR-2018
01-MAY-2018
30-APR-2023
unnamed tributary to Beans Creek and closed depression adjacent to property
overflow of process wastewater from a facility designed, constructed, operated, and maintained to contain all process-generated wastewater plus the runoff from a 25-year, 24-hour rainfall event
single stage lagoon with 6.5 million gallon capacity
0213
03-JAN-2025 10:45AM

Other DWR permits at this site

No other permits found.

Permit Documents

View
ApplicationTDA Approval Letter13-NOV-2024
ApplicationTDA Checklist 13-NOV-2024
ApplicationTDA Review Letter 13-NOV-2024
ApplicationFinal CNMP13-NOV-2024
ApplicationEPA Forms 1 and 2B 13-NOV-2024
ApplicationSigned Docs13-NOV-2024
ApplicationP Index13-NOV-2024
Inspection Report2024 CEI Oct18-OCT-2024
Report2021 Annual Report16-OCT-2024
Report2023 Annual Report16-OCT-2024
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections

16-OCT-2024CAFO Non-SamplingIn Compliance
26-SEP-2019CAFO Non-SamplingIn Compliance
30-MAY-2018CAFO Non-SamplingIn Compliance
06-APR-2017CAFO Non-SamplingIn Compliance
09-AUG-2016CAFO Non-SamplingIn Compliance
30-JUN-2015CAFO Non-SamplingIn Compliance
14-OCT-2014CAFO Non-SamplingIn Compliance