6293R. D. Robinson and Jimmy Tosh Farms370 Hudson Springs Road SharonWeakleyJacksonView Map

Permit Information

TN0074942
CAFO-Individual
Reissuance
R. D. Robinson and Jimmy Tosh Farms
Seven barn hog operation holding 960 head each (5,350 head total). Manure is stored in two separate lagoons and then applied to cropland located on the property.
I
R
PW
17-OCT-2022
11-JUL-2022
08-NOV-2022
15-NOV-2022
13-JAN-2023
01-FEB-2023
31-JAN-2028
unnamed tributary to Middle Fork Obion River
a no discharge system except for wastewater discharges resulting from catastrophic, chronic, or other rain event larger than a 25-year, 24-hour rainfall event
Two anaerobic lagoons with holdin capacity osf 16.186 mgd and 14.473 mgd respectively.
0213
07-SEP-2023 02:20PM

Other DWR permits at this site

No other permits found.

Permit Documents

View
Inspection ReportCEIs from 6 September 2001 to 19 January 200619-JAN-2006
Image20 August 2008 - Unauthorized mortality management20-AUG-2008
ApplicationR.D. Robinson Farms Design Drawings May 199804-SEP-2013
ApplicationR.D. Robinson Farms Operation,Maintenance & Utilization Plans May 199804-SEP-2013
Notice of DeficiencyLetter and comments from TDA to Jimmy Tosh and R.D. Robinson following review of CAFO permit application. 2-6-1406-FEB-2014
Draft PermitCAFO-TN0074942 Permit 2014 (Draft)10-JUN-2014
Draft PermitCAFO-TN0074942 Permit 2014 (Draft with Name change)20-JUN-2014
PermitCAFO-TN0074942 Permit 2014 (Final)11-AUG-2014
ReportR.D. Robinson and Jimmy Tosh Farms 2014 Annual Report02-MAR-2015
Inspection Report8-7-15 R. D. Robinson - Jimmy Tosh CEI Inspection Documents13-AUG-2015
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections

16-JUN-2022CAFO Non-SamplingOut of Compliance
05-JUN-2018CAFO Non-SamplingIn Compliance
07-AUG-2015CAFO Non-SamplingIn Compliance
19-APR-2011CAFO Non-SamplingNotice of Deficiency
28-APR-2010CAFO Non-SamplingFollow-up Inspection Required
28-MAY-2009Pretreatment TAV and File ReviewFollow-up Inspection Required
20-AUG-2008CAFO Non-SamplingNOV
17-JUN-2008CAFO Non-SamplingIn Compliance
28-FEB-2007CAFO Non-SamplingIn Compliance
18-JAN-2006Compliance Eval (non-sampling) (CEI)In Compliance