Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO Name
5207Clinton WWTP #1799 Melton Hill DrClintonAndersonKnoxville

Permit Information

TN0026506
Individual
Reissuance
Clinton Utilities Board
Clinton WWTP #1
Treatment of municipal sewage
M
M
MW
31-OCT-2022
15-NOV-2022
04-APR-2023
08-MAY-2023
01-JUN-2023
31-MAY-2028
Clinch River Mile 56.9
treated municipal wastewater from Outfall 001
Activated sludge and trickling filter processes preceded by primary clarification and followed by secondary clarification, chlorination and dechlorination. Sludge is aerobically digested and dewatered via vacuum filtration for landfill disposal.
4952
3
08-JUL-2024 03:41PM

Other DWR permits at this site

Permit Documents

View
FormMOR-Sep-2425-OCT-2024
Inspection ReportCompliance Inspection July 202424-JUL-2024
LetterJuly 2024 CEI Response24-JUL-2024
Monitoring ReportJune 2024 MOR22-JUL-2024
Monitoring ReportApr 24 MOR15-MAY-2024
LetterPCI+Form-2414-MAY-2024
Letter23.0624 Approval letter 2024041212-APR-2024
Monitoring ReportClinton UB Biosolids Report March 202409-APR-2024
Monitoring ReportFebruary 2024 MOR29-FEB-2024
Monitoring ReportJanuary 2024 MOR31-JAN-2024
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections

03-JUL-2024Compliance Eval (non-sampling) (CEI)In Compliance
10-MAY-2024Pretreatment Compliance (oversight)In Compliance
19-APR-2023Pretreatment TAV and File ReviewIn Compliance
12-JUL-2022Compliance Eval (non-sampling) (CEI)In Compliance
22-APR-2022Pretreatment Compliance (oversight)In Compliance
29-APR-2021Pretreatment AuditIn Compliance
30-NOV-2020Compliance Eval (non-sampling) (CEI)In Compliance
11-FEB-2020Pretreatment TAV and File ReviewIn Compliance
29-APR-2019Pretreatment Compliance (oversight)In Compliance
21-DEC-2018Compliance Eval (non-sampling) (CEI)In Compliance

Wastewater Engineering Plans Review

23.0624ApprovedCDMJB3/22/20244/12/2024Miller Rd. Forcemain Phase 1
23.0066Review CompletePERTNH2/6/20233/6/2023WWTP Headworks Renovations
22.0772ApprovedCDA. Bahour1/23/20231/23/2023Cozy Preserve Subdivision
22.0636ApprovedCDTNH10/6/202210/26/2022Clinton Downtown Streetscapes Sewer Line Rehabilitation & Relocation
22.0202ApprovedCDMNU8/8/20228/22/2022Clinton Utilities Board 2022 Sanitary Sewer Rehabilitation Phase I
21.0450ApprovedCDTNH6/8/20216/29/2021Heritage Landing
21.0419ApprovedCDMJB6/14/20216/14/2021Forest Ave Extension
21.0398ApprovedCDAWJ5/12/20215/13/2021Proposed Sewer Extension Lee Road
20.0223ApprovedCDJAH4/17/20204/17/2020Clinton Utilities Board Standard Specifications
20.0134ApprovedCDJAH4/17/20204/17/2020Anderson Higher Education Center