Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO Name
5048Cowan STP300 Looney St.CowanFranklinColumbia

Permit Information

TN0021644
Individual
Reissuance
City of Cowan
Cowan STP
Treatment of municipal wastewater in an oxidation ditch activated sludge plant with chlorination/dechlorination
I
M
MW
03-JUN-2021
27-JUL-2016
23-JUN-2021
27-JUL-2021
31-AUG-2021
01-FEB-2022
31-JAN-2027
Boiling Fork Creek at mile 13.4
treated municipal wastewater from Outfall 001
Oxidation ditch activated sludge plant with chlorination/dechlorination
4952
.4
08-JUL-2024 03:49PM

Other DWR permits at this site

Permit Documents

View
MemoWPN23.0583 ARP Memo 2023102727-OCT-2023
Letter23.0308 Approval TDEC letter 12-JUL-2023
LetterCompliance Evaluation Inspection26-APR-2023
Letter23.0053 Approval letter21-MAR-2023
EmailPT IWS 202306-FEB-2023
LetterPT IWS Reminder03-FEB-2023
Letter23.0053 Utility Approval letter27-JAN-2023
PermitFinal permit; Issue 8/31/2131-AUG-2021
ReportCowan TNPOP final report 18AUG2118-AUG-2021
Draft PermitDraft permit; PN 7/27/2127-JUL-2021
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections

14-APR-2023Compliance Eval (non-sampling) (CEI)In Compliance
25-AUG-2020Compliance Eval (non-sampling) (CEI)In Compliance
17-APR-2018Compliance Eval (non-sampling) (CEI)In Compliance
01-APR-2016Compliance Eval (non-sampling) (CEI)In Compliance
14-AUG-2013Compliance Eval (non-sampling) (CEI)NOV
13-DEC-2011Performance Audit (PAI)NOV
30-SEP-2011Compliance Eval (non-sampling) (CEI)In Compliance
12-JAN-2010Compliance Eval (non-sampling) (CEI)NOV

Wastewater Engineering Plans Review

23.0583PendingPERTNH10/9/202310/27/20232023 Cowan Sewer System Rehabilitation
23.0308PendingCDA. Bahour6/14/20237/12/2023City of Cowan, TN - Sewer System Standard Specifications
23.0053PendingCDMJB1/27/20233/21/2023Slagtown Residential Subdivision
19.0302ApprovedCDJAH7/23/20197/25/2019Franklin County South Middle School