Site IDSiteLocationCityCountyEFO Name
5018Millington STP #27920 Epperson Mill RoadMillingtonShelbyMemphis

Permit Information

TN0021067
Individual
Reissuance
City of Millington
Millington Wastewater Treatment Plant
Treatment of municipal wastewater through oxidation ditch and sand filtration with chlorine disinfection
M
M
MW
15-JUN-2022
20-JUN-2022
26-JUL-2022
29-AUG-2022
01-SEP-2022
30-JUN-2027
Big Creek at mile 6.9
treated municipal wastewater from Outfall 001
Dual circular oxidation ditches with clarifiers to sand filters with chlorine contact and post aeration. Sludge is held in a lagoon until land applied by injection. Sludge held in lagoons intil land applied by injection.
4952
5.8
08-JUL-2024 03:49PM

Other DWR permits at this site

  • 1 - 1 of 1
  • 1 - 1 of 1

Permit Documents

View
LetterWPN24.0455 Approval Letter 2024070202-JUL-2024
LetterWPN23.0641 Approval Letter 2024043030-APR-2024
LetterResponse to Director's Order WPC23-007412-APR-2024
LetterWPN 22.0687 Extension Letter 03.05.202405-MAR-2024
LetterResponse to NOV dated 25-MAY-2313-JUN-2023
Notice of ViolationNOV for effluent violations on EPA's QNCR from January to April 2023 25-MAY-2023
Letter23.0132 TDEC Approval Letter21-APR-2023
LetterResponse to NOV dated 16-FEB-2303-MAR-2023
Notice of ViolationNOV for effluent violations on EPA's QNCR from September to October 2022 16-FEB-2023
LetterWPN22.0740 Approval Letter 2022121515-DEC-2022
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections

06-OCT-2009Biosolids InspectionIn Compliance
07-AUG-2020Compliance Biomonitoring (CBI)In Compliance
17-APR-2024Compliance Eval (non-sampling) (CEI)Pending
06-MAR-2018Compliance Eval (non-sampling) (CEI)In Compliance
06-JAN-2016Compliance Eval (non-sampling) (CEI)In Compliance
23-JAN-2014Compliance Eval (non-sampling) (CEI)In Compliance
03-JUL-2012Compliance Eval (non-sampling) (CEI)In Compliance
17-NOV-2009Compliance Eval (non-sampling) (CEI)In Compliance
03-OCT-2007Compliance Eval (non-sampling) (CEI)In Compliance
17-AUG-2022Performance Audit (PAI)In Compliance

Wastewater Engineering Plans Review

24.0455ApprovedCDTNH6/11/20247/2/2024Huntington Estates SD Phase 4
23.0641ApprovedCDTNH11/2/20234/30/2024Northfork Creek East Basin Outfall Sewer
23.0132ApprovedCDCourtlandV3/9/20234/21/2023Fork River Commons Sewer Extension Millington TN
22.0740ApprovedCDTNH12/1/202212/15/2022Huntington Estates SD Phase 3
22.0687ApprovedCDTNH11/29/202212/13/2022Thornhill Estates Phase 4
22.0076ApprovedCDMNU2/17/20223/7/2022Thornhill Estates
21.0795ApprovedCDTNH1/10/20221/10/2022Huntington Estates Phase 2
21.0794ApprovedCDTNH1/10/20221/10/2022Huntington Estates Phase 1
21.0224ApprovedCDMNU7/1/20217/14/2021Windstone Estates
21.0212ApprovedCDZachSeiden3/12/20216/30/2021Barrett Oaks