Site IDSiteLocationCityCountyEFO NameGIS
11734Water & Wastewater Authority of Wilson County - Cedar Grove FacilityCedar Grove RoadLebanonWilsonNashvilleView Map

Permit Information

SOP-04015
SOP
Reissuance
Water and Wastewater Authority of Wilson County
Cedar Grove Facility
Septic tanks, effluent collection system, deep cell facultative pond and drip irrigation; Reissue with an additional 2.2+/- acres of drip disposal area adjacent to the Woodland Ridge development.
N/A
M
DI
21-OCT-2022
31-OCT-2022
08-NOV-2022
13-JAN-2023
01-MAY-2023
30-APR-2028
Graves Branch ~ 5,000 feet. No discharge authorized from this system.
Domestic effluent
Septic tanks, effluent collection system, deep cell facultative pond and drip irrigation
.0239
01-JUL-2024 11:14AM

Other DWR permits at this site

  • 1 - 2 of 2
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
NR1004.226Adenus Solutions Group, LLC--Water & Wastewater Authority of Wilson County - Cedar Grove Cedar Grove Road Treatment Facility Force Main extension for Carroll Oakland SchoolARAPInactiveN/ANashville-22-NOV-201030-JUN-2015
TNR147550Water and Wastewater Authority of Wilson CountyPipeline installation for Carroll OaklandCGPInactiveN/ANashville-22-NOV-2010-
  • 1 - 2 of 2

Permit Documents

View
Inspection ReportCEI drip field only. Follow up inspection. Unable to locate drip field other than around levee.26-AUG-2024
Inspection ReportCEI follow up drip field only (wooded drip field west of Lagoon)26-AUG-2024
Inspection ReportCEI drip field only26-AUG-2024
Inspection ReportCEI drip field follow up inspection26-AUG-2024
Inspection ReportCEI drip field only 26-AUG-2024
ReportOperation and Maintenance Inspection Schedule27-JUN-2024
ReportRCVD VIA EMAIL 01-MAY-23: report re: updated inspection frequency from Jenny Nichols01-MAY-2023
PermitFinal Permit06-JAN-2023
Draft PermitDraft Permit08-NOV-2022
ApplicationRenewal Application07-OCT-2022
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

no data found

Inspections

11-DEC-2009Compliance Evaluations (non-NPDES)Minor Deficiency Noted
17-MAY-2019Compliance Evaluations (non-NPDES)Out of Compliance
10-JAN-2024Compliance Evaluations (non-NPDES)Out of Compliance
01-FEB-2024Compliance Evaluations (non-NPDES)Out of Compliance
11-JUN-2024Compliance Evaluations (non-NPDES)Out of Compliance
19-JUL-2024Compliance Evaluations (non-NPDES)Out of Compliance

Wastewater Engineering Plans Review

18.0188ApprovedCDARa3/23/20183/27/2018Cedar GroveTreatment Facility
09.0188ApprovedFMA. Bahour3/17/20094/13/2009Carrol-Oakland School
04.1397Approved--12/2/20042/11/2005CEDAR GROVE ROAD TREATMENT FACILITY