Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO Name
5174Manchester Water and Sewer Department736 West High StreetManchesterCoffeeColumbia

Permit Information

TN0025038
Individual
Reissuance
City of Manchester
Municipal POTW
Treatment of municipal sewage by extended aeration activated sludge (oxidation ditch) and UV disinfecting
M
M
MW
27-JUL-2023
19-JUL-2023
27-JUL-2023
05-DEC-2023
09-FEB-2024
01-MAR-2024
28-FEB-2029
Duck River at mile 268.5
treated municipal wastewater from Outfall 001
Oxidation ditch treatment with chlorine disinfection and dechlorination. Sludge is aerobically digested for land application.
4952
4.3
29-OCT-2024 12:20PM

Other DWR permits at this site

  • 1 - 2 of 2
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
TNB025038Manchester STP-BiosolidsReissuanceN/AColumbia25-JUL-201425-JUL-201430-APR-2019
TNR181153Manchester Water and Sewer DepartmentWastewater Treatment Plant ImprovementsCGPInactiveN/AColumbia-23-NOV-2009-
  • 1 - 2 of 2

Permit Documents

View
Letter24.0778 Plans Approval LTR 2024101616-OCT-2024
Letter2024 Self-Imposed Moratorium Manhole B49 Oct02-OCT-2024
LetterWPN23.0608 Approval Letter 2024080808-AUG-2024
Notice of ViolationPT SAR NOV Failure to sample biosolids17-JUN-2024
Email2024 Taps Approved by City14-JUN-2024
Letter2024 Discharge Notification due to Coffee St. & Madison St. Disagreement June14-JUN-2024
EmailEmail regarding Biosolids Sampling13-JUN-2024
Letter2024 Self-Imposed Moratorium for A39 & A43 Response June10-JUN-2024
Letter2024 Self-Imposed Moratorium for I141A Response June10-JUN-2024
Letter2024 Self-Imposed Moratorium for B43 Response June10-JUN-2024
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

Chronic OverflowsLetterSelf-imposed moratorium on connections to the wastewater collection system that ultimately flow to Manhole A43.4/30/2024Active
Chronic OverflowsLetterSelf-imposed moratorium on connections to the wastewater collection system that ultimately flow to Manhole A39.4/30/2024Active
Chronic OverflowsLetterSelf-imposed moratorium on connections to the wastewater collection system that ultimately flow to Manhole B49.10/2/2024Active
Chronic OverflowsLetterSelf-imposed moratorium on connections to the wastewater collection system that ultimately flow to Manhole I141A.5/7/2024Active
Chronic OverflowsLetterSelf-imposed moratorium on connections to the wastewater collection system that ultimately flow to Manhole B43.5/16/2024Active
I/IPermitorder closed--reverts to permit conditions4/4/2024Watch List75

Inspections

23-FEB-2006Compliance Eval (non-sampling) (CEI)In Compliance
23-FEB-2006Pretreatment Compliance (oversight)In Compliance
10-JAN-2007Pretreatment TAV and File ReviewIn Compliance
19-SEP-2007Performance Audit (PAI)NOV
20-AUG-2008Compliance Sampling (CSI)In Compliance
17-DEC-2008Pretreatment TAV and File ReviewIn Compliance
07-OCT-2009Compliance Eval (non-sampling) (CEI)Minor Deficiency Noted
13-JAN-2010Pretreatment AuditIn Compliance
13-JAN-2011Compliance Eval (non-sampling) (CEI)Minor Deficiency Noted
13-APR-2011Pretreatment Compliance (oversight)In Compliance

Wastewater Engineering Plans Review

24.0799IncompleteCDRGO10/24/202410/30/2024Blackburn and Rogers
24.0778InactiveCDRGO10/24/1010/16/2024Basin I Sewer Rehabilitation
23.0608ApprovedCDTNH8/6/20248/8/2024Basins A, B, E, F, H, I, & K Sewer Rehabilitation
24.0395ApprovedCDRGO5/19/20245/21/2024Laurel View Residential Subdivision
23.0760Review CompletePERTNH12/5/20231/2/20242022 ARP Sewer Rehabilitation Project
23.0373ApprovedCDMJB8/21/20238/22/2023Haley Drive Townhomes
23.0247ApprovedCDMJB5/15/20236/1/2023Stonehenge Residential Development (158 lots)
23.0080ApprovedCDA. Bahour5/15/20235/16/2023Manchester Water and Sewer Standard Specifications
23.0065ApprovedCDMJB4/20/20234/28/2023Simply Southern Residential Subdivision (76 lots)
22.0528ApprovedCDA. Bahour8/17/20229/13/2022MWSD 2022 Sewer Repairs