Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO NameGIS
6643Abernathy Concrete Co., Inc.734 South First StreetPulaskiGilesColumbiaView Map

Permit Information

TNG110118
RMCP
Active
Abernathy Concrete Co., Inc.
Ready Mix Concrete Plant
N/A
SW
20-FEB-2024
07-MAR-2024
07-MAR-2024
07-MAR-2024
31-OCT-2027
Richland Creek
Outfall 001 as a non-discharging outfall; sampling required if discharge occurs. Stormwater runoff is discharged through Outfall SW1
process-large settling basin/pond; storm water-gravel filter berms to filter solids from storm water runoff
3273
07-MAR-2024 03:34PM

Other DWR permits at this site

No other permits found.

Permit Documents

View
LetterCompliance Evaluation letter & ICIS report19-MAY-2015
LetterCompliance Evaluation Inspection31-MAY-2017
Notice of Intent (NOI)RCVD 08-DEC-17: RMCP NOI by William Abernathy.08-DEC-2017
Notice of Coverage (NOC)2017 Notice of Coverage11-DEC-2017
Old PermitTNG110118 NOC11-DEC-2017
LetterCompliance Evaluation Inspection24-MAY-2019
LetterCompliance Evaluation Inspection03-AUG-2021
EmailExpired permit, emailed to remind the need for re-application..30-OCT-2023
LetterCompliance Evaluation Inspection14-NOV-2023
Notice of Intent (NOI)UPDATED 06-MAR-24: NOI w/ maps by William Abernathy to RCVD 20-FEB-24: RMCP NOI by William Abernathy20-FEB-2024
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections

23-OCT-2023Compliance Eval (non-sampling) (CEI)In Compliance
19-JUL-2021Compliance Eval (non-sampling) (CEI)In Compliance
09-MAY-2019Compliance Eval (non-sampling) (CEI)In Compliance
17-MAY-2017Compliance Eval (non-sampling) (CEI)In Compliance
06-MAY-2015Compliance Eval (non-sampling) (CEI)In Compliance
21-AUG-2012Compliance Eval (non-sampling) (CEI)In Compliance