Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO Name
5027Church Hill STPVFW Road (STP) 300 East Main Blvd(City Hall)Church HillHawkinsJohnson City

Permit Information

TN0021253
Individual
Reissuance
City of Church Hill
Church Hill POTW
Treatment of municipal sewage by extended aeration activated sludge (oxidation ditch) and ultraviolet light disinfection
M
M
MW
13-FEB-2024
31-JAN-2024
05-MAR-2024
16-APR-2024
17-MAY-2024
01-JUN-2024
31-MAY-2029
Holston River at mile 136.5
treated domestic, commercial, and industrial wastewaters from Outfall 001
treatment of municipal sewage
4952
2.5
08-OCT-2024 08:30AM

Other DWR permits at this site

Permit Documents

View
Monitoring ReportCity of Church Hill September 2024 MOR 15-OCT-2024
LetterPT Program Modification Preliminary Approval ERP02-OCT-2024
EmailPT Audit Response 0830-SEP-2024
EmailPT Audit Response 08 Reply with Status Summary30-SEP-2024
Monitoring ReportCity of Church Hill August 2024 MOR 18-SEP-2024
EmailPT Audit Response 07 Reply16-SEP-2024
EmailPT Audit Response 07 Permits for Review11-SEP-2024
EmailPT Audit Response 06 Reply06-SEP-2024
LetterPT Audit Response 0602-SEP-2024
EmailPT Audit Responses 01-05 Reply30-AUG-2024
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

Inspections

16-JUL-2024Pretreatment AuditOut of Compliance
11-JUN-2024Compliance Eval (non-sampling) (CEI)Out of Compliance
11-JUN-2024Sanitary Sewer Overflow Non-SamplingOut of Compliance
10-OCT-2023Pretreatment Follow-upIn Compliance
07-SEP-2023Pretreatment TAV and File ReviewIn Compliance
18-AUG-2022Pretreatment Compliance (oversight)Out of Compliance
23-MAR-2022Sanitary Sewer Overflow Non-SamplingOut of Compliance
23-MAR-2022Compliance Eval (non-sampling) (CEI)Out of Compliance
10-AUG-2021Pretreatment TAV and File ReviewOut of Compliance
18-SEP-2020Pretreatment Compliance (oversight)In Compliance

Wastewater Engineering Plans Review

20.0694ApprovedCDA. Bahour12/21/202012/22/2020City of Church Hill Island View Drive Sewerline Extension
18.0481ApprovedotherMNU7/16/20187/17/2018Deerfield Circle
17.0233ApprovedPSMNU5/5/20175/5/2017Greenland PS Upgrade
17.0120ApprovedPSMNU2/9/20172/17/2017Phipps Bend PS Valve Installation
16.0730ApprovedLPCSMNU9/7/20169/22/2016West Morgan Street
14.0757ApprovedSTPMODA. Bahour10/7/201411/12/2014Wastewater Treatment Plant Sludge Press
14.0192ApprovedLINEMNU4/7/20146/30/2014Carters Valley Sewer Extension
13.0282Review CompletePERJMS5/29/20137/3/20132013 CDBG - City of Church Hill WWTP Improvements
12.0480Review CompletePERJMS7/26/20128/16/2012CDBG-2012 - Church Hill Sewer System Improvements Project
14.0374InactiveSTPMODA. Bahour6/4/2014-Sludge Press Builiding and Sludge Press