94797TVA Mt. Pleasant-Elk Ridge 161kV TL Upgrades7913 Mount Joy RoadMt. PleasantMauryColumbia

Permit Information

NRS23.156
ARAP
Minor Alterations to Wetlands
Inactive
Tennessee Valley Authority (TVA)
TVA Mt. Pleasant - Elk Ridge TL Upgrades
TVA proposes to replace approximately 25.5 miles of overhead ground wire (OHGW) with optical ground wire (OPGW) on the existing Mt. Pleasant-Elk Ridge 161-kV transmission line (TL) in Giles, Marshall, and Maury counties
N/A
03-OCT-2023
26-SEP-2023
03-OCT-2023
03-OCT-2023
25-SEP-2023
07-APR-2025
Sugar Creek, multiple wetlands
26-NOV-2024 12:53PM

Other DWR permits at this site

  • 1 - 3 of 3
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
TNR192226Tennessee Valley Authority (TVA)TVA Mt. Pleasant-Elk Ridge 161kV TL UpgradesCGPTerminationN/AColumbia-13-FEB-2023-
TNR191370Tennessee Valley Authority (TVA)TVA - Mt. Pleasant Substation Circuit SwitcherCGPInactiveN/AColumbia-06-JAN-2014-
NRS23.156bTennessee Valley Authority (TVA)TVA Mt. Pleasant - Elk Ridge TL UpgradesARAPActiveN/AColumbia03-OCT-202325-SEP-202307-APR-2025
  • 1 - 3 of 3

Permit Documents

View
Notice of TerminationNOT 26-NOV-2024
LetterAnnual Maintenance Fee Notice Letter15-JUL-2024
EmailAvoid Maury Co streams in no work period 05-OCT-2023
EmailNotice of Coverage Email03-OCT-2023
Permit23.156A Permit 25-SEP-2023
Environmental ReviewTWRA Seasonal Limits 3/15 to 4/3014-SEP-2023
EmailTWRA Receipt for inquiry 11-SEP-2023
Environmental ReviewProof of submittal to TWRA for T&E Review 11-SEP-2023
Environmental ReviewImpact Lat/Longs 11-SEP-2023
Environmental ReviewChad response will look at WTLs 11-SEP-2023