5776Etowah Utilities Board dba Etowah Utilities Wastewater Treatment Plant275 County Road 850EtowahMcMinnChattanooga

Permit Information

TN0063771
Individual
Reissuance
City of Etowah
Etowah STP
Treatment of municipal sewage
M
M
MW
07-FEB-2022
02-FEB-2022
16-FEB-2022
29-MAR-2022
02-MAY-2022
01-JUN-2022
31-MAY-2027
Conasauga Creek at mile 8.0
treated municipal wastewater from Outfall 001
Mechanical screening followed by oxidation ditches, secondary clarification, chlorination, dechlorination and post aeration drying beds to landfill
4952
1.2
25-OCT-2024 02:05PM

Other DWR permits at this site

  • 1 - 2 of 2
  • 1 - 2 of 2

Permit Documents

View
Monitoring ReportMOR Sep 202409-OCT-2024
MemoWPN24.0500 ARP Memo 2024071818-JUL-2024
LetterPCI letter Jul 202303-AUG-2023
FormPCI Form 202326-JUL-2023
ReportPT Apr 2023 SAR06-APR-2023
LetterPT PC/LL Final Approval20-MAR-2023
Public Notice DocumentPT PC/LL Public Notice09-MAR-2023
LetterPT PC/LL Preliminary Approval23-JAN-2023
Monitoring ReportMOR Dec 2022 & SSO Report12-JAN-2023
ReportPT Oct 2022 SAR14-OCT-2022
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections

21-FEB-2007Compliance Eval (non-sampling) (CEI)NOV
09-AUG-2007Pretreatment AuditNOV
25-NOV-2008Pretreatment Compliance (oversight)Order Requested
15-JUL-2009Pretreatment TAV and File ReviewIn Compliance
27-SEP-2010Pretreatment Compliance (oversight)NOV
28-JUL-2011Pretreatment TAV and File ReviewIn Compliance
24-MAY-2012Pretreatment AuditMinor Deficiency Noted
28-AUG-2012Compliance Eval (non-sampling) (CEI)In Compliance
04-OCT-2012Sanitary Sewer Overflow Non-SamplingNotice of Deficiency
15-AUG-2013Pretreatment Compliance (oversight)In Compliance

Wastewater Engineering Plans Review

12.0222ApprovedPERPhil Simmo5/9/20125/18/2012SRF Clean Water State Revolving Fund
12.0484Review CompletePERJMS7/26/20128/16/2012CDBG-2012 - Etowah I&I Improvements Project
12.0417ApprovedCAP/ERPhil Simmo8/16/201210/1/2012Etowah CAP/ER
13.0292Review CompletePERJMS5/29/20137/3/20132013 CDBG - City of Etowah Sewer Line Rehabilitation
13.0521ApprovedREHABPhil Simmo8/14/20139/9/2013State Revolving Fund Sanitary Sewer Sub-Basin B Rehabilitation
14.0149ApprovedIMPMNU3/12/20145/8/2014CDBG Sanitary Sewer Sub-Basin B Improvments
16.0622Review CompleteotherMTS8/3/20168/23/2016SRF-Rehabilitation Sub Basin B
18.0198Approved-MNU3/28/20184/23/20182017 Etowah Sewage System
24.0500Review CompletePERTNH6/24/20247/18/2024Etowah Replacement of North Industrial Park Pump Station and Force Main
24.0562IncompleteCDMJB7/22/2024-North Industrial Park Pump Station and Force Main