Site IDSiteLocationCityCountyEFO Name
5053McEwen STP aka McEwen WWTP199 South StMcEwenHumphreysNashville

Permit Information

TN0021741
Individual
Reissuance
City of McEwen
McEwen STP
Treatment of municipal sewage via Sequencing Batch Reactor
I
M
MW
20-JAN-2023
09-FEB-2023
11-APR-2023
15-MAY-2023
01-AUG-2023
31-JUL-2028
08-FEB-2010
Blue Creek at mile 16.2
Treated municipal wastewater from Outfall 001
SBR treatment system with chlorination and de-chlorination and post equalization after upgrade from 0.45 MGD to 0.6 MGD STP
4952
.6
08-JUL-2024 03:49PM

Other DWR permits at this site

  • 1 - 3 of 3
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
TNR241684City of McEwen2017 WWTP ImprovementsCGPInactiveN/ANashville-24-MAY-2017-
NR1804.076City of McEwenCity of McEwen Wastewater Treatment Plan ImprovementsARAPInactiveN/ANashville-13-APR-201820-APR-2020
TNB021741McEwen STP-BiosolidsInactiveN/ANashville---
  • 1 - 3 of 3

Permit Documents

View
Report Oct 2016 PT SAR28-OCT-2016
Letter03-MAR-14 CBI letter & ICIS entry form03-JUL-2014
Memo1-Mar-07 memo re: PAI NOV response01-MAR-2007
Memo1-Mar-07 memo, NOV response re: sewer rehabilitation01-MAR-2007
Email13-Apr-16 Wastewater Program Update13-APR-2016
Engineering Report16-0694 Approval Engineering Report27-SEP-2016
Letter16-0694 Approval letter27-SEP-2016
Email16-0694 E-mail22-SEP-2016
Letter16-0694 Transmittal letter23-AUG-2016
Letter17-0186 Approval letter23-MAR-2017
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

Chronic OverflowsPermitSelf-Imposed Moratorium started on 12/23/2003. Subsequent total moratorium on connections imposed via Commisioner's Order WPC12-0113. See Item 7, under Order & Assessment Section (page 21). While order is now closed, the system remains under a moratorium via the permit.6/5/2013Active72

Inspections

17-MAR-2014Compliance Biomonitoring (CBI)In Compliance
26-SEP-2019Compliance Eval (non-sampling) (CEI)Out of Compliance
14-AUG-2012Compliance Sampling (CSI)NOV
21-DEC-2010Follow-upNOV
02-JUN-2011Performance Audit (PAI)NOV
24-JUN-2010Performance Audit (PAI)NOV
07-JUN-2006Performance Audit (PAI)NOV
22-JUN-2021Pretreatment AuditOut of Compliance
18-SEP-2015Pretreatment AuditOut of Compliance
31-AUG-2010Pretreatment AuditNOV

Wastewater Engineering Plans Review

13.0624InactiveCAP/ERPhil Simmo10/9/2013-McEwen Corrective Action Plan/Engineering Report
24.0041ApprovedCDTNH1/18/20244/17/2024Rachford Development Water and Sewer Line Extension
20.0523ApprovedCDZachSeiden10/1/202010/14/2020Blair Blvd. Gravity Sewer Line Extension
20.0030ApprovedCDA. Bahour1/27/20202/25/2020HWY 70 S Sanitary Sewer Rehabilitation
13.0625ApprovedCMOMPhil Simmo10/9/2013-McEwen Management, Operations, and Maintenance
17.0197ApprovedIMPMTS4/19/20177/1/2017Wastewater Treatment Plant
23.0487Review CompletePERTNH9/1/20239/29/2023City of McEwen Sewer Repair
14.0298InactivePER-5/9/2014-2014 CDBG-Wastewater Treatment Plant Upgrades
13.0310Review CompletePERJMS5/29/20137/3/20132013 CDBG - City of McEwen Sewer System Rehabiliation
16.0694ApprovedPSGCG9/26/20169/27/2016Highway 70 Pump Station