Site IDSiteLocationCityCountyEFO Name
5185Harriman STP504 Bullard Ford RoadHarrimanRoaneKnoxville

Permit Information

TN0025437
Individual
Reissuance
City of Harriman
Harriman STP
Screening, grit removal, biological treatment via oxidation ditches and center feed-peripheral withdrawal clarifiers, and chlorine disinfection. Waste activated sludge is aerobically digested, dewatered with a belt filter press prior to land application.
M
M
MW
30-NOV-2020
03-DEC-2020
15-DEC-2020
20-JAN-2021
01-FEB-2021
31-JAN-2026
Outfall 001 -Tennessee River at mile 567 or Outfall 002 - Emory River (10.5)
Treated municipal wastewater from Outfalls 001 or 002
Screening, grit removal, biological treatment via oxidation ditches and center feed-peripheral withdrawal clarifiers, and chlorine disinfection. Waste activated sludge is aerobically digested, dewatered with a belt filter press prior to land application.
4952
1.5
08-JUL-2024 03:41PM

Other DWR permits at this site

Permit Documents

View
Monitoring ReportOctober 2024 MOR11-NOV-2024
Monitoring ReportSeptember 2024 MOR30-SEP-2024
Monitoring ReportAugust 2024 MOR31-AUG-2024
Monitoring ReportJuly 2024 MOR31-JUL-2024
Monitoring ReportJune 2024 MOR10-JUL-2024
Monitoring ReportApril 24 MOR10-MAY-2024
Monitoring ReportPermit Renewal labs10-MAY-2024
Monitoring ReportEmory River Flow Rpt Apr 2410-MAY-2024
Inspection ReportReconnaissance Inspection-April-2416-APR-2024
MemoWPN24.0230 ARP Memo 2024040909-APR-2024
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

OverflowsEFO CommunicationRobert Ramsey email 4/16/194/17/2019Closed

Inspections

11-APR-2024Compliance AssistanceIn Compliance
07-APR-2023Compliance Eval (non-sampling) (CEI)In Compliance
28-SEP-2021Compliance Biomonitoring (CBI)In Compliance
24-JUN-2020Compliance AssistanceIn Compliance
19-MAR-2020Compliance AssistanceIn Compliance
14-MAY-2019Compliance Eval (non-sampling) (CEI)In Compliance
20-SEP-2017Compliance Eval (non-sampling) (CEI)In Compliance
17-FEB-2016Compliance Eval (non-sampling) (CEI)In Compliance
11-FEB-2014Compliance Eval (non-sampling) (CEI)In Compliance
16-JUL-2012Compliance Eval (non-sampling) (CEI)In Compliance

Wastewater Engineering Plans Review

00.0259ApprovedSTDSPECMNU3/2/20004/4/2000STD SPECS
12.0488Review CompletePERJMS7/26/20128/16/2012CDBG-2012 - Harriman Sewer System Improvements Project
14.0450ApprovedLINEMNU7/14/20148/20/2014State Route 29
18.0239ApprovedCDA. Bahour5/17/20185/17/2018Highland View, Phase 2
18.0687Review Complete-Jim McAdoo8/1/20188/3/2018Wastewater Treatment Plant Clarifier No 1
23.0304ApprovedCDA. Bahour7/13/20237/13/2023Harriman Utility Board Standard Specifications
23.0607ApprovedCDMJB11/9/202311/27/2023Pine Ridge Road Sewer Extension
23.0600ApprovedCDMJB12/4/202312/12/2023Emory Creek Subdivision Phase 1
24.0181ApprovedCDTNH3/8/20244/9/2024ARPA Sanitary Sewer Rehabilitation
21.0584Review CompleteCDTNH7/27/2021-Clarifier No. 2 Rehabilitation and Repainting