Site IDSiteLocationCityCountyEFO Name
5059Portland STP124 Morningside DrivePortlandSumnerNashville

Permit Information

TN0021865
Individual
Incomplete
City of Portland
Portland STP
Upgrading the treatment systems by adding 2 SBRs for a total of 4 SBRs to increase the capacity from 1.9 to 2.85 MGD. The new design will not increase loads of oxygen demanding pollutants and incidental degradation is justified by the applicant.
M
M
MW
28-JUN-2024
03-JUL-2024
20-JUN-2019
06-AUG-2019
01-DEC-2019
01-JAN-2020
31-AUG-2024
Summers Branch at mile 8.6 to the Red River
treated municipal wastewater from Outfall 001
Sequencing Batch Reactor (SBR) activated sludge with chlorination, dechlorination, and post aeration. Sludge: was, imhoff, to land appl.
4952
2.85
03-JUL-2024 03:01PM

Other DWR permits at this site

  • 1 - 2 of 2
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
TNR246722City of Portland, Tennessee2020 Wastewater Treatment Plant ExpansionCGPActiveN/ANashville-10-JUL-202330-SEP-2026
TNB021865Portland STP-BiosolidsIncompleteN/ANashville---
  • 1 - 2 of 2

Permit Documents

View
LetterList of connections to which Portland was legally obligated prior to the moratorium associated with Consent Order 04-058526-JUL-2006
ReportLab report for Cd from 3/10 CBI18-MAR-2010
ReportLab report for Pp from 3/10 CBI18-MAR-2010
ReportBivens complaint JRS TR 3-30-1030-MAR-2010
ImageMap of Portland Sewer System20-SEP-2010
ApplicationRCVD VIA EMAIL 12-FEB-14: NPDES app by Kenneth Wilber.12-FEB-2014
ApplicationSigned Page 903-APR-2014
Draft PermitDraft Permit (for 5/4/2014 PN)19-MAY-2014
LetterSAR NOV09-JUN-2014
LetterRCVD VIA EMAIL 13-JUN-14: letter to Jim McAdoo re: comments on Draft by Dana Wright of TCWN.13-JUN-2014
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

I/I:Permit ViolationsCommissioner's OrderMoratorium on Connections see Item 8 under Order & Assessment Section (page 15).4/18/2017Active58

Inspections

17-JUN-2024Compliance Eval (non-sampling) (CEI)Out of Compliance
14-JUN-2023Pretreatment TAV and File ReviewIn Compliance
18-AUG-2022Compliance Eval (non-sampling) (CEI)Out of Compliance
07-JUL-2022Sanitary Sewer SystemIn Compliance
02-JUN-2022Pretreatment Compliance (oversight)In Compliance
25-MAY-2021Pretreatment AuditOut of Compliance
03-MAR-2021Follow-upOut of Compliance
07-JUL-2020Compliance Eval (non-sampling) (CEI)Out of Compliance
01-JUL-2020Sanitary Sewer Overflow Non-SamplingOut of Compliance
11-JUL-2019Pretreatment Compliance (oversight)Out of Compliance

Wastewater Engineering Plans Review

19.0252Review CompleteC&E ReviewSJH4/30/2019-Portland 2018 Annual CMOM Report
24.0325ApprovedCDRGO4/30/20245/20/2024Bracken Estates - Sanitary Sewer Plans
24.0289ApprovedCDMJB5/23/20245/23/2024Parkside Pointe SPS & Force main
24.0227ApprovedCDMJB4/1/20245/30/2024Parkside Pointe
24.0160ApprovedCDMJT3/1/20244/1/2024Sanitary Sewer Rehab of Portland Sudden Service
24.0148ApprovedCDJKM2/27/20245/3/2024Harbin Sandye Avenue - Sanitary Sewer Collection Plans
24.0015ApprovedCDTNH2/2/20242/5/2024N Harris Ln Sewer Extension
23.0747ApprovedCDTNH3/1/20243/26/2024HWY 52E No. 1 Lift Station Relocation
23.0629ApprovedCDTNH1/29/20241/29/2024Twin Lakes
23.0560ApprovedCDJKM2/26/20242/28/2024Richland Estates Subdivision – Sanitary Sewer Collection Plans