Site IDSiteLocationCityCountyEFO Name
4916Greenbrier STP1223 Sugar Camp DrGreenbrierRobertsonNashville

Permit Information

TN0020621
Individual
Reissuance
City of Greenbrier
Greenbrier STP
treatment of municipal wastewater by sequencing batch reactor with ultraviolet disinfection
I
M
MW
29-SEP-2023
11-OCT-2023
23-JAN-2024
27-FEB-2024
01-APR-2024
31-MAR-2029
unnamed tributary at mile 0.5 to Carr Creek at mile 10.3
treated municipal wastewater from Outfall 001
Sequencing Batch Reactor with ultraviolet disinfecting.
4952
.74
04-OCT-2024 08:10AM

Other DWR permits at this site

  • 1 - 3 of 3
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
TNR240610City of GreenbrierWWTP ExpansionCGPActiveN/ANashville-12-APR-201630-SEP-2026
NRS01.143City of Greenbrier-ARAPInactiveN/ANashville05-JUL-2001-05-JUL-2003
TNB020621Greenbrier STP-BiosolidsInactiveN/ANashville26-JUN-201426-JUN-201430-APR-2019
  • 1 - 3 of 3

Permit Documents

View
LetterTIE/TRE Notification- failed two consecutive Biomonitoring tests during the 3rd Quarter testing period, hypothesis is water hardness due to drought03-SEP-2024
Letter24.0516 Plans Approval LTR 2024081919-AUG-2024
EmailBIO results for the 3rd quarter- Failure12-AUG-2024
ReportPT IWS18-JUN-2024
EmailPT IWS Reminder31-MAY-2024
Monitoring ReportApril eMOR07-MAY-2024
PermitFinal permit; Issue 2/27/2427-FEB-2024
Monitoring ReportJan 2024 eMOR14-FEB-2024
Draft PermitDraft permit; PN 1/23/24 (re public notice to revise pretreatment language from approved to dormant status)23-JAN-2024
Monitoring ReportDecember 2023 eMOR and PAA testing sheets13-JAN-2024
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

Chronic OverflowsCommissioner's OrderTotal Moratorium for connections to the Greenbrier Collection System.WPC21-0065 with connection credits to be authorized by the city.1/6/2022Active52

Inspections

01-NOV-2023Pretreatment TAV and File ReviewIn Compliance
03-NOV-2022Pretreatment Compliance (oversight)In Compliance
16-DEC-2021Pretreatment AuditOut of Compliance
05-APR-2021Compliance Biomonitoring (CBI)Out of Compliance
18-MAR-2021Sanitary Sewer Overflow Non-SamplingOut of Compliance
17-OCT-2019Pretreatment Compliance (oversight)Out of Compliance
29-NOV-2018Pretreatment TAV and File ReviewIn Compliance
26-JUL-2018Compliance Eval (non-sampling) (CEI)Out of Compliance
26-JUL-2018Sanitary Sewer Overflow Non-SamplingOut of Compliance
30-NOV-2017Pretreatment Compliance (oversight)In Compliance

Wastewater Engineering Plans Review

24.0516ApprovedCDRGO7/24/38/19/2024Phelps Street Sewer Line Extension
23.0347ApprovedCDTNH8/31/20239/1/2023Nelsons Reserve
23.0384ApprovedCDMJB7/21/20238/31/2023Distillery Force Main Replacement
23.0013ApprovedCDTNH1/6/20231/25/2023Greenbrier Sewer Rehabilitation ARPA
22.0025ApprovedCDMNU3/23/20224/28/2022Cattle Trails Estates
20.0624ApprovedCDAWJ12/23/20201/4/2021Westbrook Condos
17.0788ApprovedLINEA. Bahour12/19/201712/19/2017Carrs Creek S/D, Section 2
16.0457Review CompleteotherGCG6/13/20167/15/2016SRF- Contract 1-1 Greenbrier Wastewater Treatment Plant Upgrades
04.1015ApprovedSTDSPECMBS9/1/200411/10/2004STD SPECS
98.0110ApprovedPERWDM2/5/19982/25/1998STP EX