Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO Name
5185Harriman STP504 Bullard Ford RoadHarrimanRoaneKnoxville

Permit Information

TN0025437
Individual
Reissuance
City of Harriman
Harriman STP
Screening, grit removal, biological treatment via oxidation ditches and center feed-peripheral withdrawal clarifiers, and chlorine disinfection. Waste activated sludge is aerobically digested, dewatered with a belt filter press prior to land application.
M
M
MW
30-NOV-2020
03-DEC-2020
15-DEC-2020
20-JAN-2021
01-FEB-2021
31-JAN-2026
Outfall 001 -Tennessee River at mile 567 or Outfall 002 - Emory River (10.5)
Treated municipal wastewater from Outfalls 001 or 002
Screening, grit removal, biological treatment via oxidation ditches and center feed-peripheral withdrawal clarifiers, and chlorine disinfection. Waste activated sludge is aerobically digested, dewatered with a belt filter press prior to land application.
4952
1.5
08-JUL-2024 03:41PM

Other DWR permits at this site

Permit Documents

View
Monitoring ReportOctober 2024 MOR11-NOV-2024
Monitoring ReportSeptember 2024 MOR30-SEP-2024
Monitoring ReportAugust 2024 MOR31-AUG-2024
Monitoring ReportJuly 2024 MOR31-JUL-2024
Monitoring ReportJune 2024 MOR10-JUL-2024
Monitoring ReportApril 24 MOR10-MAY-2024
Monitoring ReportPermit Renewal labs10-MAY-2024
Monitoring ReportEmory River Flow Rpt Apr 2410-MAY-2024
Inspection ReportReconnaissance Inspection-April-2416-APR-2024
MemoWPN24.0230 ARP Memo 2024040909-APR-2024
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

OverflowsEFO CommunicationRobert Ramsey email 4/16/194/17/2019Closed

Inspections

11-APR-2024Compliance AssistanceIn Compliance
07-APR-2023Compliance Eval (non-sampling) (CEI)In Compliance
28-SEP-2021Compliance Biomonitoring (CBI)In Compliance
24-JUN-2020Compliance AssistanceIn Compliance
19-MAR-2020Compliance AssistanceIn Compliance
14-MAY-2019Compliance Eval (non-sampling) (CEI)In Compliance
29-NOV-2017Sanitary Sewer Overflow Non-SamplingOut of Compliance
20-SEP-2017Compliance Eval (non-sampling) (CEI)In Compliance
17-FEB-2016Compliance Eval (non-sampling) (CEI)In Compliance
11-FEB-2014Compliance Eval (non-sampling) (CEI)In Compliance

Wastewater Engineering Plans Review

00.0259ApprovedSTDSPECMNU3/2/20004/4/2000STD SPECS
12.0488Review CompletePERJMS7/26/20128/16/2012CDBG-2012 - Harriman Sewer System Improvements Project
14.0450ApprovedLINEMNU7/14/20148/20/2014State Route 29
18.0239ApprovedCDA. Bahour5/17/20185/17/2018Highland View, Phase 2
18.0687Review Complete-Jim McAdoo8/1/20188/3/2018Wastewater Treatment Plant Clarifier No 1
23.0304ApprovedCDA. Bahour7/13/20237/13/2023Harriman Utility Board Standard Specifications
23.0607ApprovedCDMJB11/9/202311/27/2023Pine Ridge Road Sewer Extension
23.0600ApprovedCDMJB12/4/202312/12/2023Emory Creek Subdivision Phase 1
24.0181ApprovedCDTNH3/8/20244/9/2024ARPA Sanitary Sewer Rehabilitation
21.0584Review CompleteCDTNH7/27/2021-Clarifier No. 2 Rehabilitation and Repainting