Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO Name
5003Decherd Water Works STP311 4th Ave. SouthDecherdFranklinColumbia

Permit Information

TN0020508
Individual
Reissuance
City of Decherd
Decherd Water Works STP
Treatment of municipal sewage by primary clarifier, two oxidation ditch units, nutrient removal and ultraviolet disinfection
M
M
MW
01-MAR-2022
12-JAN-2022
09-MAR-2022
19-APR-2022
23-MAY-2022
01-JUL-2022
30-JUN-2027
Wagner Creek at mile 2.4
treated municipal wastewater from Outfall 001
treatment of municipal sewage by primary clarifier prior to two oxidation ditch units, nutrient removal and ultraviolet disinfection following the secondary treatment process
4952
2.5
29-OCT-2024 12:15PM

Other DWR permits at this site

  • 1 - 2 of 2
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
TNR182347City of DecherdDecherd Wastewater Treatment Plant ExpansionCGPInactiveN/AColumbia-05-APR-201930-SEP-2026
TNB020508Decherd STP-BiosolidsInactiveN/AColumbia---
  • 1 - 2 of 2

Permit Documents

View
Letter2024 Missing 2023 TIR/TRE Study & 3rd Qtr Biomonitoring Failure Response Oct10-OCT-2024
Letter2024 Operator in Charge Oct04-OCT-2024
Letter2024 Missing 2023 TIR/TRE Study & 3rd Qtr Biomonitoring Failure Sept20-SEP-2024
Letter2024 PCI Response May10-MAY-2024
EmailSCADA stopped reporting effluent values. Granted approval to use influent flow data for DMR calculations. 12-APR-2024
Form2024 PCI Form Mar11-APR-2024
Inspection Report2024 PCI Mar11-APR-2024
LetterDelegation of signatory authority Dana Douglas21-MAR-2024
LetterPT Del Signatory for A Bonomo13-MAR-2024
Letter2024 CEI Response Feb14-FEB-2024
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

Chronic OverflowsLetterSelf-imposed moratorium on connections to the wastewater collection system that ultimately flow to the Noles Street MH2953/30/2020Active

Inspections

27-FEB-2013Pretreatment AuditCRM Requested
19-MAR-2009Compliance Eval (non-sampling) (CEI)Follow-up Inspection Required
27-MAR-2024Pretreatment Compliance (oversight)In Compliance
30-NOV-2022Compliance Eval (non-sampling) (CEI)In Compliance
02-MAR-2022Pretreatment TAV and File ReviewIn Compliance
11-MAR-2021Pretreatment Compliance (oversight)In Compliance
26-MAR-2020Pretreatment TAV and File ReviewIn Compliance
26-FEB-2019Pretreatment Compliance (oversight)In Compliance
29-NOV-2018Compliance Eval (non-sampling) (CEI)In Compliance
22-AUG-2018Compliance Eval (non-sampling) (CEI)In Compliance

Wastewater Engineering Plans Review

03.0729ApprovedSTDSPECMBS7/28/20038/18/2003STD SPECS
13.0631ApprovedIMPA. Bahour10/16/201311/7/20132012 Sewer System Improvements Contract B, C
14.0065ApprovedIMPMNU1/29/20143/14/20142010 Sewer System Improvements
16.0577ApprovedPERMTS10/5/201612/6/20162016 Wastewater Treatment Plant
18.0046ApprovedSTPEXPAWJ3/15/20183/26/2018Wastewater Treatment Plant Expansion
17.0834ApprovedLINEA. Bahour4/4/20184/4/2018US Highway 41A
18.0956ApprovedCDA. Bahour12/27/201812/27/2018Third & Cherry Street Sewer Extension
19.0083ApprovedCDA. Bahour3/27/20193/27/2019US Highway 41A Pump Station And Sewer Line Extension, Phase 2
19.0301ApprovedCDJAH6/12/20196/18/2019Franklin County North Middle School
19.0546ApprovedCDMNU8/28/20199/20/2019Proposed McAfee-Cofer Residential S/D Warren Chapel Road