Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO NameGIS
5085Dover STP409 Forrest StreetDoverStewartNashvilleView Map

Permit Information

TN0022667
Individual
Reissuance
Town of Dover
Dover STP
Treatment of municipal sewage with sequencing batch reactors and disinfecting by ultraviolet light
I
M
MW
17-MAY-2024
22-JUL-2009
04-JUN-2024
16-JUL-2024
19-AUG-2024
01-JUN-2025
31-MAY-2030
Barkley Reservoir at Cumberland River mile 88.6
treated municipal wastewater from Outfall 001
Sequencing Batch Reactor (SBR) treatment facility with ultraviolet disinfection. The sludge is dewatered in a Phase Separator Dewatering Unit (Box Separator) prior to disposal at Clarksville Disposal LLC landfill.
4952
.6
23-DEC-2024 09:40AM

Other DWR permits at this site

Permit Documents

View
Report Oct 2017 PT SAR 18-OCT-2017
Inspection Report01-JUN-15 CBI letter13-JUL-2015
Inspection Report01-JUN-15 CBI report13-JUL-2015
Letter18_0813 Plans Approval Letter19-DEC-2018
Letter18_0813 Plans Cover Letter19-DEC-2018
Inspection Report19-MAR-15 PCI form27-JUL-2015
Inspection Report19-MAR-15 PCI letter27-JUL-2015
Letter19.0717 Dover Donelson Approval Letter18-NOV-2019
Environmental Review19.0717 Dover Donelson Environmental Review18-NOV-2019
Form19.0717 Dover Donelson Parkway Checklist12-NOV-2019
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections

05-DEC-2024Pretreatment Compliance (oversight)Out of Compliance
19-DEC-2023Pretreatment TAV and File ReviewIn Compliance
01-DEC-2022Pretreatment Compliance (oversight)In Compliance
10-NOV-2021Pretreatment AuditOut of Compliance
20-DEC-2019Compliance Eval (non-sampling) (CEI)In Compliance
20-DEC-2019Sanitary Sewer SystemIn Compliance
24-OCT-2019Pretreatment Compliance (oversight)In Compliance
24-OCT-2018Pretreatment TAV and File ReviewIn Compliance
09-NOV-2017Pretreatment Compliance (oversight)Out of Compliance
08-DEC-2016Pretreatment AuditOut of Compliance

Wastewater Engineering Plans Review

24.0859PendingCDTNH11/21/202412/9/20242024 Town of Dover Gravity Sewer Extension - Donelson Parkway Annexation
24.0722PendingCDTNH9/19/20249/23/20242024 ARPA Dover Collection System Improvements
24.0112PendingPERTNH2/14/20242/28/2024Dover Wastewater Collection System Preliminary Engineering Report
20.0602ApprovedCDAWJ12/8/202012/15/20202019 CDBG Dover Sewer Rehabilitation
19.0717ApprovedCDJAH11/15/201911/18/2019Donelson Parkway Low Pressure Sewer Extension
18.0813ApprovedCDMTS9/28/201812/18/20182018 Church Street Lift Station Upgrades
14.0443ApprovedREHABMNU7/9/20148/19/20142014 Sewer System Rehabilitation
13.0287Review CompletePERJMS5/29/20137/3/20132013 CDBG - Town of Dover Sewer System Rehabilitation and I/I Correction