Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO Name
5820Camden HCR Lagoon and Spray IrrigationHildon King RoadCamdenBentonJackson

Permit Information

TN0064611
Individual
Reissuance
City of Camden
Camden Wastewater Treatment Facility
Treatment of municipal sewage via lagoons and discharge by hydrograph controlled release with accompanying land application system permitted separately
I
M
MW
20-SEP-2023
02-FEB-2018
21-SEP-2023
17-OCT-2023
27-NOV-2023
01-DEC-2023
30-NOV-2028
Cypress Creek at mile 12.8
treated municipal wastewater from Outfall 001
2 cell partial-mix facultative lagoon system, storage pond, chlorination and dechlorination, with a land application system parallel to discharge
4952
.5
23-DEC-2024 09:35AM

Other DWR permits at this site

  • 1 - 9 of 9
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
TNB064611Camden STP-BiosolidsInactiveN/AJackson---
TNR121832City of CamdenCamden SRF WWTP Plant Additions - Phase 2 2016 Land Application SystemCGPInactiveN/AJackson-18-MAY-2016-
TNR121313City of Camden-CGPInactiveN/AJackson-24-JUN-2011-
TNR121645City of CamdenCamden WWTP Additions - Phase 1 Renovation and OptimizationCGPActiveN/AJackson-27-JUN-201430-SEP-2026
SOP-15022City of CamdenCamden STPSOPReissuanceN/AJackson01-AUG-202101-AUG-202131-JUL-2026
NR1602.026City of CamdenCamden SRF WWTP Phase IIARAPInactiveN/AJackson09-MAY-201609-MAY-201631-DEC-2017
NR1102.082City of CamdenCypress Creek/ high flow channel bank stabilizationARAPInactiveN/AJackson25-AUG-201125-AUG-201125-AUG-2012
NR1102.048City of Camden-ARAPInactiveN/AJackson24-JUN-201124-JUN-201124-JUN-2012
NR1102.047City of CamdenHigh Flow Channel RepairARAPInactiveN/AJackson24-JUN-201124-JUN-201124-JUN-2012
  • 1 - 9 of 9

Permit Documents

View
SpreadsheetDO Study Results02-APR-2012
MemoDeputy Commisioners Summary - Dilution Ratio Report03-APR-2012
Memo6/3/2013 Meeting Notes03-JUN-2013
Memo6/3/2013 Meeting List03-JUN-2013
LetterLetter for Camden Meeting and Stream Survey17-JUN-2013
Inspection ReportCamden TAV checklist 031114.pdf11-MAR-2014
MemoMarch 13, 2014 Meeting Notes13-MAR-2014
LetterCamden TAV 4-11-1411-APR-2014
LetterCamden TAV 03.11.14 letter 11-APR-2014
FormCompliance Biomonitoring (CBI) 2014 356007-MAY-2014
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

I/IAt this time, there are reportedly no chronic overflow locations within the collection system. Past problems with overflow at the STP associated with industrial discharges have been resolved. Problems with overflow at the STP related to storage capacity are well on their way to being resolved via spray irrigation.wdm9/29/2016Closed78

Inspections

28-MAR-2024Pretreatment TAV and File ReviewIn Compliance
25-MAY-2023Pretreatment Compliance (oversight)In Compliance
26-MAY-2022Compliance Eval (non-sampling) (CEI)In Compliance
21-OCT-2021Pretreatment AuditIn Compliance
07-MAY-2021Pretreatment TAV and File ReviewIn Compliance
25-MAR-2020Pretreatment Compliance (oversight)In Compliance
12-AUG-2019Pretreatment TAV and File ReviewIn Compliance
28-DEC-2018Compliance Eval (non-sampling) (CEI)In Compliance
28-DEC-2018Sanitary Sewer SystemIn Compliance
15-AUG-2018Follow-upOut of Compliance

Wastewater Engineering Plans Review

13.0280Review CompletePERJMS5/29/20137/3/20132013 CDBG - City of Camden Sewer System Rehabilitation
12.0707InactiveCAP/ERPhil Simmo12/7/2012-City of Camden CAP/ER