5213
City of Sneedville STP
306 Harrison Street
Sneedville
Hancock
Johnson City
Permit Information
Permit Number
TN0026638
Permit Type
Individual
Status
Reissuance
Permittee Name
Town of Sneedville
Project Name
Sneedville STP
Activity Description
AER-O-MOD activated sludge treatment system with influent equalization and post chlorination
Permit Rating
I
Facility Classification
M
Discharge Code
MW
Application Received
30-JUL-2024
Application Returned
06-JUN-2024
Application Complete
30-JUL-2024
Public Notice Date
19-NOV-2024
Issuance Date
23-DEC-2024
Effective Date
01-JAN-2025
Expiration Date
31-DEC-2029
Modification Date
Termination Date
Receiving Stream
Clinch River at mile 177.4
Effluent Description
treated municipal wastewater from Outfall 001
Treatment Description
AER-O-MOD activated sludge treatment system with influent equalization and post chlorination
SIC Code
4952
SIC 2
SIC 3
SIC 4
Design Flow Rate [MGD]
.155
Record Last Updated
23-DEC-2024 04:10PM
Other DWR permits at this site
Go
Actions
No other permits found.
Permit Documents
Search All Documents
View Permit
FileNet Documents
View
File Type
Description
Document Date
Monitoring Report
Sneedville WWTP November 2024 MOR
13-DEC-2024
Draft Permit
Draft permit; PN 11/19/24
19-NOV-2024
Monitoring Report
Sneedville WWTP October 2024 MOR
15-NOV-2024
Monitoring Report
Sneedville WWTP September 2024 MOR
17-OCT-2024
Monitoring Report
Sneedville WWTP August 2024 MOR
16-SEP-2024
Monitoring Report
Sneedville WWTP July 2024 MOR
12-AUG-2024
Application
Updated application with completed Table B by JMT, Inc.
30-JUL-2024
Letter
Response to CEI corrective actions
12-JUL-2024
Monitoring Report
Sneedville WWTP June 2024 MOR
12-JUL-2024
Email
RDVD VIA EMAIL 07_09_2024 Email Additional Follow Up Question from Response to NOV Received 06_26_2024
09-JUL-2024
row(s) 1 - 10 of 72
Next
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.
Moratorium
Problem
Mechanism
Result
Action Date
Status
Percent Annual I I
Overflows:WWTP Overload
EFO Communication
Chris Rhodes email dated 4-Apr-2019
4/4/2019
Watch List
62
Inspections
Inspection Date
Type
Result
10-MAY-2024
Compliance Eval (non-sampling) (CEI)
Out of Compliance
10-MAY-2024
Sanitary Sewer Overflow Non-Sampling
Out of Compliance
11-SEP-2019
Compliance Eval (non-sampling) (CEI)
Out of Compliance
11-SEP-2019
Sanitary Sewer Overflow Non-Sampling
Out of Compliance
11-APR-2017
Compliance Assistance
Immediately Corrected During Inspection
19-DEC-2014
Follow-up
CRM Requested
30-JUN-2014
Compliance Eval (non-sampling) (CEI)
Order Requested
22-SEP-2009
Compliance Eval (non-sampling) (CEI)
NOV
10-MAY-2006
Reconnaissance (RI)
NOV
row(s) 1 - 9 of 9
Wastewater Engineering Plans Review
Project no
Plans Status
Type
Reviewer
Date Received
Approved Date
Project Name
22.0509
Pending
CD
MNU
8/5/2022
8/24/2022
City of Sneedville Sanitary Sewer Improvements Phase 6
22.0508
Pending
CD
MNU
8/5/2022
9/22/2022
S.R. 33; (Main Street), Bridge Over Greasy Rock Creek, L.M. 11.77 (IA) Sanitary Sewer Relocation
18.0604
Review Complete
PPD
AWJ
7/27/2018
-
Sneedville Sewer System Improvements Project
15.0324
Approved
STPMOD
MNU
5/26/2015
7/7/2015
WWTP Blower Improvement Project
14.0800
Approved
LINE
A. Bahour
3/25/2014
3/26/2015
Phase 2 & 3 Sewer Replacement