Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO Name
5046Union City STP aka A.L. Strub Wastewater Treatment PlantLynch LaneUnion CityObionJackson

Permit Information

TN0021580
Individual
Reissuance
City of Union City
A.L. Strub WWTP
Treatment of municipal sewage
M
M
MW
28-FEB-2020
11-MAR-2020
21-JUL-2020
06-SEP-2020
01-NOV-2020
31-OCT-2025
07-NOV-2005
North Fork Obion River at mile 8.2
treated municipal wastewater from Outfall 001
WAS to aerobic digesters to spray irrigation
4952
5
31-OCT-2024 10:30AM

Other DWR permits at this site

  • 1 - 2 of 2
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
TNR056411A.L. Strub Wastewater Treatment Plant-TMSPNo ExposureN/AJackson13-OCT-200913-OCT-200914-MAY-2014
TNB021580Union City STP-BiosolidsInactiveN/AJackson---
  • 1 - 2 of 2

Permit Documents

View
Report April 2018 PT SAR 20-APR-2018
Letter16-0426 Letter22-JUN-2016
Letter16-0426 Ref21-JUN-2016
Letter16-0910 Approval let6ter08-DEC-2016
Environmental Review16-0910 Information15-NOV-2016
Letter16-0979 Approval letter13-JAN-2017
Engineering Specifications16-0979 Information19-DEC-2016
Letter17-0526 Letter01-SEP-2017
Letter17-0526 Ref24-AUG-2017
Letter17.0436 Approval letter31-JUL-2017
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections

25-JUN-2024Compliance Eval (non-sampling) (CEI)In Compliance
24-APR-2024Pretreatment TAV and File ReviewIn Compliance
18-MAY-2023Pretreatment Compliance (oversight)In Compliance
21-SEP-2022Pretreatment AuditOut of Compliance
04-AUG-2022Compliance Eval (non-sampling) (CEI)In Compliance
03-SEP-2021Pretreatment Compliance (oversight)In Compliance
25-AUG-2020Compliance Eval (non-sampling) (CEI)In Compliance
22-APR-2020Pretreatment TAV and File ReviewIn Compliance
11-APR-2019Pretreatment Compliance (oversight)In Compliance
25-JUN-2018Compliance Eval (non-sampling) (CEI)In Compliance

Wastewater Engineering Plans Review

24.0564PendingPERTNH7/23/20248/7/2024City of Rives Sewer Rehabilitation Phase 1
18.0966Approved-MNU12/27/20181/15/2019Sewer Line Repairs for Union City
17.0526ApprovedLINEMNU8/31/20178/31/2017Houser Creek Crossing Phase 2
17.0436Approved-A. Bahour7/27/20177/31/2017Industrial Park Utility
16.0979ApprovedLINEA. Bahour12/19/20161/13/2017Barkley Taylor Street S/D
16.0910ApprovedLINEA. Bahour12/8/201612/8/2016Houser Creek Crossing, Phase 1
16.0426ApprovedLINEMNU6/3/20166/21/2016Briar Meadows S/D Sewer Line
15.0305ApprovedLINEA. Bahour6/30/20156/30/2015Wastewater Line Extensions
15.0267ApprovedLINEA. Bahour5/4/20155/6/2015Ware Park Apartments
14.0077Approved-MNU2/4/20143/19/2014Sewer Imprv. for William Country Sausage and Woodland Mills