Site IDSiteLocationCityCountyEFO Name
5141Johnson City Brush Creek WWTP857 Riverview DriveJohnson CityWashingtonJohnson City

Permit Information

TN0024244
Individual
Reissuance
Johnson City
Brush Creek WWTP
Treatment of municipal sewage using mechanical screen, grit chamber, primary clarifiers, activated sludge aeration basins, secondary clarifiers, chlorine contact chamber, and dechlorination.
M
M
MW
04-MAR-2021
08-MAR-2016
30-MAR-2021
24-AUG-2021
30-SEP-2021
01-OCT-2021
30-SEP-2026
Watauga River Mile 16.4
Treated municipal wastewater from Outfall 001
WAS to aerobic dig to land application
4952
16
07-AUG-2024 09:30AM

Other DWR permits at this site

  • 1 - 3 of 3
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
TNRX50137Brush Creek POTW-TMSPNo ExposureN/AJohnson City---
TNR161755City of Johnson CityBrush Creek Wastewater treatment plantCGPInactiveN/AJohnson City-06-JAN-2016-
TNB024244Johnson City Brush Creek STP-BiosolidsInactiveN/AJohnson City---
  • 1 - 3 of 3

Permit Documents

View
LetterWPN24.0594 Approval Letter 2024090405-SEP-2024
LetterWPN 24.0321 Approval Letter16-AUG-2024
Monitoring ReportBrush Creek WWTP July 2024 MOR 14-AUG-2024
Inspection ReportCEI for SSO Non-Sampling Inspection09-AUG-2024
Monitoring ReportBrush Creek WWTP October 2023 MOR09-AUG-2024
Corrective Action PlanJohnson City Brush Creek WWTP Compliance Inspection Response09-AUG-2024
EmailJohnson City Brush Creek WWTP Compliance Inspection Response Email Receipt09-AUG-2024
Monitoring ReportBrush Creek WWTP June 2024 MOR 12-JUL-2024
Inspection ReportJohnson City Brush Creek WWTP TN0024244 Compliance Evaluation Inspection (CEI) report resulting from June 20, 2024 inspection12-JUL-2024
LetterWPN24.0332 Approval Letter 2024070203-JUL-2024
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

Chronic OverflowsLetterSelf-Imposed moratorium triggered at MH #3971, 2244 Eddie Williams Rd for chronic overflows. Permittee advised of moratorium via inspection report dated 02-JUL-2020 and confirmed in follow up letter dated 03-NOV-2020.11/3/2020Closed59

Inspections

20-JUN-2024Sanitary Sewer Overflow Non-SamplingIn Compliance
20-JUN-2024Compliance Eval (non-sampling) (CEI)In Compliance
18-AUG-2023Pretreatment Compliance (oversight)In Compliance
27-SEP-2022Compliance Eval (non-sampling) (CEI)Out of Compliance
27-SEP-2022Sanitary Sewer Overflow Non-SamplingOut of Compliance
24-AUG-2022Pretreatment TAV and File ReviewIn Compliance
09-SEP-2021Pretreatment Compliance (oversight)In Compliance
25-MAR-2021Pretreatment Follow-upIn Compliance
02-SEP-2020Pretreatment AuditIn Compliance
05-JUN-2020Sanitary Sewer Overflow Non-SamplingOut of Compliance

Wastewater Engineering Plans Review

24.0594ApprovedCDMJT8/2/20249/4/2024BROOKDALE VILLAGE
24.0321ApprovedCDJKM7/31/20248/16/2024Suncrest Commons
24.0332Approved-MJT5/2/20247/2/2024Watauga Rd. Gravity Sewer Extension
24.0198ApprovedCDMJT3/19/20243/22/2024Snowden Terrace Sewer Line Extension
23.0602ApprovedCDTNH10/17/202311/14/2023E. Main St. Sewer Replacement Project
23.0218ApprovedCDA. Bahour5/10/20235/10/2023Johnson City Sewerline Construction Specifications Review
22.0763Approved-CourtlandV12/16/20223/24/2023Sinking Creek Sewer Pump Station Upgrades Project
23.0085ApprovedCDCourtlandV2/16/20233/17/2023INDIAN RIDGE RESIDENTIAL DEVELOPMENT
23.0037ApprovedCDMJB1/18/20231/25/2023Johnson City Nissan Expansion
22.0549ApprovedCDA. Bahour8/25/20229/21/2022Landy Development Sewer Extension