Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO Name
2109Hamilton County Water & Wastewater Treatment Authoritycounty-wideChattanoogaHamiltonChattanooga

Permit Information

SOP-89044
SOP
Reissuance
Hamilton County Water & Wastewater Treatment Authority (WWTA)
Municipal Satellite Collection System
Sewage collection system to Chattanooga interceptor sewer system and Moccasin Bend STP
N/A
M
CS
05-FEB-2024
22-JAN-2024
06-FEB-2024
09-APR-2024
18-JUL-2024
01-AUG-2024
31-JUL-2029
TN River and tributaries; distances vary
No discharge allowed
Collection system
29-OCT-2024 12:20PM

Other DWR permits at this site

No other permits found.

Permit Documents

View
ReportHCWWTA City of Red Bank Mgmt Agreement 10310331-OCT-2003
ReportHCWWTA Signal Mtn collect system 09160916-SEP-2009
ReportHCWWTA PSLP background memo impose $8 fee 01211021-JAN-2010
ReportWWTA sues east ridge Chatt TFP media report 07031203-JUL-2012
ReportHCWWTA easement questions ChattTFP media report 09011201-SEP-2012
ReportQtrly report 2nd qtr 201421-JUL-2014
Old PermitFinal SOP04-AUG-2014
Inspection ReportEPA Region IV WWTA collection system and Signal Mountain CEI September 201415-SEP-2014
LetterNon-Compliance Letters from HCWWTA04-DEC-2014
LetterTDEC Approval HCWWTA WWP 14-0839 Pottery Lane Pump Stn10-DEC-2014
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

Chronic OverflowsLetterLetter 12/18/201812/18/2018Active

Inspections

16-NOV-2023Sanitary Sewer SystemOut of Compliance
01-NOV-2018Sanitary Sewer Overflow Non-SamplingOut of Compliance
20-JUL-2017Compliance Evaluations (non-NPDES)Out of Compliance

Wastewater Engineering Plans Review

24.0754ApprovedCDMJB9/30/202410/14/2024Soddy-Daisy Sewer Rehabilitation Phase II
24.0751IncompleteCDMJB9/27/2024-Gateway Sewer Project
24.0287Review CompletePERMJB4/16/20245/21/2024Signal Mountain Infrastructure Improvements Phase 1
24.0200ApprovedCDTNH3/19/20245/16/2024West Brow Oval Pump Station Improvements (WWTA Project No.12-316, SWIG ID 2022-8571, Project WW-PDC-1
24.0188ApprovedCDMJB3/12/20245/7/2024Signal Mountain Phase 1 Infrastructure Improvements Project - SWIG 2022-8379
24.0010ApprovedCDMJB3/12/20243/13/2024Rhinehart Valley Phase 1 Forcemain Upgrades
23.0793Review CompletePERTNH12/5/202312/15/2023East Ridge Phase 4 Rehabilitation Project
23.0757ApprovedCDTNH12/5/202312/15/2023East Ridge Phase 4 Rehabilitation Project SWIG ID: 2022-8669
23.0157RApproved-TNH9/26/202310/5/2023Soddy Daisy Sewer Rehabilitation
23.0551ApprovedCDMJT9/20/20239/26/2023EAST RIDGE PHASE 3 REHABILITATION PROJECT