Site IDSiteLocationCityCountyEFO Name
170421Pleasant Grove Farms - Phase 2Pleasant Grove RoadWestmorelandSumnerNashville

Permit Information

TNR246028
CGP
Active
5D Land LLC
Pleasant Grove Farms
Construction of 74 residential single-family detached homes
21-JUL-2022
07-JUN-2022
08-AUG-2022
08-AUG-2022
30-SEP-2026
Trammel Creek
03-AUG-2023 11:58AM

Other DWR permits at this site

  • 1 - 8 of 8
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
TNR2463495D Land LLCPleasant Grove Farms - Phase 2CGPActiveN/ANashville-05-MAY-202330-SEP-2026
NR2304.0765D Land LLCPleasant Grove Farms - Road Crossing Reach 3 ARAPActiveN/ANashville-05-MAY-202307-APR-2025
NR2304.0775D Land LLCPleasant Grove Farms - Outfall Reach 3ARAPActiveN/ANashville-25-APR-202307-APR-2025
NR2304.0785D Land LLCPleasant Grove Farms - Utility Crossing Reach 3ARAPActiveN/ANashville-25-APR-202307-APR-2025
NR2304.0755D Land LLCPleasant Grove Farms - Force Main ARAP Reach 2ARAPActiveN/ANashville-25-APR-202307-APR-2025
NR2304.0745D Land LLCPleasant Grove FarmsARAPActiveN/ANashville-25-APR-202307-APR-2025
NR2304.0795D Land LLCPleasant Grove Farms - Sewer Crossing Reach 4ARAPActiveN/ANashville-25-APR-202307-APR-2025
NR2204.2045D Land LLCPleasant Grove FarmsARAPActiveN/ANashville-08-AUG-202207-APR-2025
  • 1 - 8 of 8

Permit Documents

View
Inspection ReportStormwater Construction Non-Sampling23-APR-2024
ImageInspection Photos23-APR-2024
EmailARAP number and copy of HD21-JUL-2022
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections

23-APR-2024Stormwater Construction Non-SamplingOut of Compliance

CGP - Specific Information

Area Disturbed (acres)
33.01
Start Date
6/1/2022
Estimated End Date
6/1/2023
Streams
No
Wetlands
No
Exceptional TN Waters (ETW)
No
ETW Comment
-
Threatened and Endangered Species 1 mile radius
No
Threatened and Endangered Species 5 miles downstream
Yes
Unavailable Conditions Waters
No
Unavailable Conditions Waters Comment
-
EPSC Plan Findings
-

Contractors

Contractor 1
JR Builders LLC
Start Date
6/1/2022
Contractor 2
-
Start Date
-
Contractor 3
-
Start Date
-
Contractor 4
-
Start Date
-
Contractor 5
-
Start Date
-
Contractor 6
-
Start Date
-