Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO NameGIS
171661Tree Clearing Project37 AIRPORT RDFAYETTEVILLELincolnColumbiaView Map

Permit Information

TNR182860
CGP
Termination
Fayetteville-Lincoln County Regional Airport Authority
Tree Clearing Project
clearing and grubbing of existing trees with some tree topping
17-AUG-2022
14-SEP-2022
14-SEP-2022
30-SEP-2026
Walker Creek
Construction Stormwater Runoff
EPSC Devices
16-DEC-2024 08:07AM

Other DWR permits at this site

No other permits found.

Permit Documents

View
Notice of TerminationNOT request16-DEC-2024
LetterAnnual Maintenance Fee Notice Letter15-JUL-2024
Notice of Coverage (NOC)NOC15-SEP-2022
SWPPPRevision for wetland work14-SEP-2022
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections

no data found

CGP - Specific Information

Area Disturbed (acres)
9.5
Start Date
9/14/2022
Estimated End Date
10/10/2022
Streams
Yes
Wetlands
Yes
Exceptional TN Waters (ETW)
No
ETW Comment
-
Threatened and Endangered Species 1 mile radius
No
Threatened and Endangered Species 5 miles downstream
No
Unavailable Conditions Waters
Siltation
Unavailable Conditions Waters Comment
-
EPSC Plan Findings
-

Contractors

Contractor 1
Curl Construction and Excavating, LLC
Start Date
9/14/2022
Contractor 2
-
Start Date
-
Contractor 3
-
Start Date
-
Contractor 4
-
Start Date
-
Contractor 5
-
Start Date
-
Contractor 6
-
Start Date
-