Site IDSiteLocationCityCountyEFO Name
2097City of La VergneMason RoadLa VergneRutherfordNashville

Permit Information

SOP-88061
SOP
Reissuance
City of La Vergne
Municipal Collection System
Collection system for sanitary wastewater to Metro Water Services
N/A
M
CS
19-SEP-2023
26-SEP-2023
12-DEC-2023
24-JAN-2024
01-APR-2024
31-MAR-2029
N/A
No discharge allowed
Collection system - 12,876 connections
3.15
04-OCT-2024 08:05AM

Other DWR permits at this site

No other permits found.

Permit Documents

View
ApplicationRCVD VIA EMAIL 19-SEP-23: SOP app by Jason Cole19-SEP-2023
ApplicationPermit renewal application26-OCT-2018
Draft PermitDraft Permit 202312-DEC-2023
Draft PermitDraft Permit 201919-FEB-2019
EmailNRS23.23112-MAR-2024
EmailMyTDEC Forms Req Notification - Event Form04-NOV-2021
EmailReminder to Renew26-SEP-2018
Email15-0557 E-mail String13-JUL-2016
Engineering Calculations16-0225 Madison Square Calcs 31-MAR-2016
Engineering Calculations16-0123 Ref02-MAR-2016
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

no data found

Inspections

10-OCT-2018Compliance Evaluations (non-NPDES)Immediately Corrected During Inspection
29-JUN-2010Compliance Evaluations (non-NPDES)Minor Deficiency Noted

Wastewater Engineering Plans Review

05.0527ApprovedSTDSPECMNU5/16/20056/10/2005STANDARD SPECIFICATIONS
14.0343ApprovedSTDSPECA. Bahour5/13/20146/3/2014City of La Vergne Standard Sewer Specifications
14.0168ApprovedLINEA. Bahour3/20/20146/4/2014Pinnacle Point, Phase IV
14.0346ApprovedLINEMNU5/22/20147/17/2014Walmart Commercial Center S/D
14.0651ApprovedLINEA. Bahour8/21/20149/12/2014Woodsong S/D, Revised Section VI
14.0749ApprovedLINEA. Bahour10/6/201412/12/2014Pinnacle Point II
14.0895ApprovedLINEA. Bahour12/4/20141/9/2015The Ridge S/D, Phase I
15.0431ApprovedPSA. Bahour8/17/20158/17/2015Cedar Ridge Sewage Pump Station Improvements
15.0417ApprovedLINEMNU7/2/20158/19/2015Centrepointe, Lots 13 & 14
15.0538Approved-MNU9/18/201510/12/2015The Villas of Central Park Phase 3