Site IDSiteLocationCityCountyEFO NameGIS
24642Northshore DevelopmentHwy 128 @ Northshore Dr.PickwickHardinJacksonView Map

Permit Information

TNR120076
CGP
Active
Pickwick Preserve, LLC Phillip Jackson
Residential development along north shore of Pickwick Lake.
16-JUL-2001
26-NOV-2001
26-NOV-2001
30-SEP-2026
01-OCT-2021
Pickwick Lake-Tennessee River
01-JUN-2023 01:51PM

Other DWR permits at this site

  • 1 - 16 of 16
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
TNR120076.01Benton Revocable Living Trust (Lenny Leon Benton, Trustee)-CGPInactiveN/AJackson-23-JUN-2016-
TNR120076.02Brian & Kim BadgerGrand Villa PH3- Lot 10CGPInactiveN/AJackson-13-OCT-2016-
TNR121045David NicholsDavid Nichols' Lot 7 in Breeze PointeCGPActiveN/AJackson-24-OCT-200830-SEP-2026
TNR121570Hank McDowellCanyon Cove Lot 5CGPInactiveN/AJackson-25-OCT-2013-
TNR121148Harry Mitchell1.316 Acre Tract-Northshore SubdivisionCGPInactiveN/AJackson-15-OCT-2009-
TNR121058Jason GriffinLot 5, Pelican PointCGPActiveN/AJackson-24-JUN-200930-SEP-2026
TNR121348John BasekBasek Property, Lot 8 ParkPlace@Northshore SubdivisionCGPInactiveN/AJackson-01-SEP-2011-
TNR120076.04Kenneth & Joyce McKenzieGrand Villa Phase 3 - Lot 8CGPActiveN/AJackson-07-JUL-202030-SEP-2026
TNR121178Lavonne BlackBlack Property-Lot 2CGPActiveN/AJackson-08-APR-201030-SEP-2026
TNR120076.06Legacy Construction and Remodeling of TN llc-CGPIncompleteN/AJackson---
TNR120076.03Logic Land CompanyPelican Pointe, Phase III, Lot 8CGPInactiveN/AJackson-08-AUG-2017-
TNR120981Newport Land Company, LLC-CGPActiveN/AJackson-22-MAY-200830-SEP-2026
TNR120076.05Opal Denise Rutledge and Barry BickesOpal Denise Rutledge - Quarry Hollow Point, Northshore DevelopmentCGPActiveN/AJackson-09-APR-2024-
TNR120982Phillip Jackson-CGPActiveN/AJackson-19-MAY-200830-SEP-2026
TNR121161Richard MurphyRichard Murphy-Northshore SubdivisionCGPActiveN/AJackson-19-NOV-200930-SEP-2026
TNR121291Robert Goetz, Jr.-CGPInactiveN/AJackson-23-MAR-2011-
  • 1 - 16 of 16

Permit Documents

View
ReportPickwick_PreserveCGPinspectionpictures10-19-0713-MAY-2008
MemoParrish_contact13-MAY-2008
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections

03-SEP-2024Stormwater Construction Non-SamplingOut of Compliance
23-JAN-2024Stormwater Construction Non-SamplingOut of Compliance
31-MAR-2008Stormwater Construction Non-SamplingNOV
23-FEB-2007Stormwater Construction Non-SamplingNOV

CGP - Specific Information

Area Disturbed (acres)
52.9
Start Date
7/1/2001
Estimated End Date
12/31/2020
Streams
Yes
Wetlands
No
Exceptional TN Waters (ETW)
No
ETW Comment
-
Threatened and Endangered Species 1 mile radius
-
Threatened and Endangered Species 5 miles downstream
Yes
Unavailable Conditions Waters
No
Unavailable Conditions Waters Comment
-
EPSC Plan Findings
-

Contractors

Contractor 1
Johnson Construction
Start Date
-
Contractor 2
Envirogreen, Inc.
Start Date
-
Contractor 3
Ronald Franks Construction, LLC
Start Date
-
Contractor 4
Phillip Jackson Construction Company
Start Date
-
Contractor 5
-
Start Date
-
Contractor 6
-
Start Date
-