175816Atmos Energy Union City North Transmission Pipeline Replacement ProjectHollie Hutchison Road, approximately one-mile southwest of the intersection of Hollie Hutchison Road and Old Fulton Harris Road, to its eastern terminus along Wolf Creek RoadUnion CityObionJacksonView Map

Permit Information

NRS24.029
ARAP
Individual Permit
Complete
Atmos Energy Corporation
Union City North Gas Pipeline Replacement
Atmos Energy Corporation proposes temporary impacts to 1.066 acres of wetlands for replacement of a natural gas pipeline near unnamed tributaries to Harris Fork Creek in Union City (Obion County).
N/A
13-MAR-2024
27-AUG-2024
06-SEP-2024
01-OCT-2024
Harris Fork Creek, Wolf Creek and unnamed tributaries
30-SEP-2024 11:38AM

Other DWR permits at this site

  • 1 - 2 of 2
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
TNR122932Atmos Energy CorporationUnion City North Transmission Pipeline Replacement ProjectCGPActiveN/AJackson-30-AUG-2024-
NR2302.037Atmos Energy CorporationUnion City North Gas Pipeline ReplacementARAPActiveN/AJackson-09-AUG-202309-AUG-2024
  • 1 - 2 of 2

Permit Documents

View
EmailPublic Notice Email30-SEP-2024
LetterApplicant Letter of Responsibility 30-SEP-2024
Public Notice DocumentPublic Notice Document30-SEP-2024
Draft PermitDraft Permit for Public Notice30-SEP-2024
Emailrequest for additional information27-AUG-2024
AddendumARAP Payment18-MAR-2024
ApplicationApplication Package13-MAR-2024
EmailAcknowledgment of Application Intent Email23-FEB-2024
LetterAcknowledgment of Application Intent23-FEB-2024
LetterLetter to Atmos Energy stating IP is required for more than 1 ac. or temporary wetland impacts in Wetland 106-FEB-2024