4986Tennessee Valley Authority (TVA) - Cumberland Fossil Plant (CUF) ReservationLinear project located at: 455 Old Scott Rd.Cumberland CityStewartNashville

Permit Information

TN0005789
Individual
Reissuance
Tennessee Valley Authority (TVA)
Cumberland Fossil Plant (CUF)
operation of coal-fired steam electric power plant with cooling water intake; TVA submitted a notice of planned participation (NOPP) to cease coal operations no later than 2028
M
P
PW, NPW, SW
30-JAN-2023
28-FEB-2023
10-OCT-2023
30-NOV-2023
01-DEC-2023
30-NOV-2028
30-NOV-2007
Cumberland River at mile 103
chemical metal cleaning wastewater from IMP 007, bottom ash sluice water, economizer ash sluice water, station sump, demineralizer (DI) sump, flue gas desulphurization (FGD) discharge, coal yard runoff pond discharge, south yard and roof drains and combustion residual leachate (CRL) from IMP 001, emergency overflow for IMP 001 (would only discharge in response to a probable maximum precipitation event) from Outfall 01A, once through condenser cooling water and discharge from IMP 001 from Outfall 002, intake screen backwash from Outfall 004 and operation of a cooling water intake structure
Settling, Chemical Precipitation, Neutralization and Discharge to Surface Water
4911
2075
03-JAN-2024 07:41PM

Other DWR permits at this site

  • 1 - 33 of 33
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
TNR192255Tennessee Valley AuthorityCumberland Combined Cycle Transmission Line FeedsCGPActiveN/ANashville-22-FEB-202430-SEP-2026
NRS21.093Tennessee Valley Authority (TVA)Cumberland Projects Minor Water WithdrawalARAPTransferN/ANashville---
TNR191811Tennessee Valley Authority (TVA)Fuel Wet Flue Gas DesulfurizationCGPInactiveN/ANashville-21-MAY-2019-
TNR191762Tennessee Valley Authority (TVA)Flue Gas Desulfurization (FGD)CGPInactiveN/ANashville-23-OCT-2018-
TNR191752Tennessee Valley Authority (TVA)Cumberland Bottom Ash Dewatering ProjectCGPInactiveN/ANashville-17-SEP-2018-
TNR191665Tennessee Valley Authority (TVA)Cumberland Fossil Plant Chemical Pond Closure ProjectCGPInactiveN/ANashville-26-JUL-2017-
TNR191532Tennessee Valley Authority (TVA)Cumberland Ash Silo Haul Road ProjectCGPInactiveN/ANashville-25-JAN-2016-
TNR191517Tennessee Valley Authority (TVA)Cumberland Fossil Plant Landfill ExplorationCGPInactiveN/ANashville-02-DEC-2015-
TNR191422Tennessee Valley Authority (TVA)Cumberland Fossil Plant Borrow StudyCGPInactiveN/ANashville-24-SEP-2014-
TNR191153Tennessee Valley Authority (TVA)Ash Pond Complex Spillway Improvement ProjectCGPInactiveN/ANashville-16-MAY-2011-
TNR190845Tennessee Valley Authority (TVA)Three Above Ground Temporary TanksCGPInactiveN/ANashville-29-JUL-2008-
TNR190825Tennessee Valley Authority (TVA)Cumberland Fossil Plant (CUF)CGPInactiveN/ANashville-10-APR-2008-
NRS23.267Tennessee Valley Authority (TVA)CUF Boat Ramp Improvement ProjectARAPActiveMinorNashville05-APR-202403-APR-202402-APR-2029
NRS23.275Tennessee Valley Authority (TVA)CUF Gypsum/Equipment Dock DredgeARAPInactiveMinorNashville01-DEC-202330-NOV-202329-NOV-2028
NRS23.273Tennessee Valley Authority (TVA)Emergency CUF Limestone Barge DredgeARAPInactiveMinorNashville05-OCT-202305-OCT-202304-OCT-2028
TNR192023Tennessee Valley Authority (TVA)TVA - Cumberland Fossil Plant - Proposed Landfill Tree ClearingCGPInactiveN/ANashville-09-NOV-202030-SEP-2026
TNR191734Tennessee Valley Authority (TVA)Cumberland Fossil Plant - South Borrow AreaCGPInactiveN/ANashville-28-JUN-201830-SEP-2026
TNR191725Tennessee Valley Authority (TVA)Cumberland Fossil Plant Main Ash Pond RepurposingCGPInactiveN/ANashville-18-JUN-201830-SEP-2026
TNR191704Tennessee Valley Authority (TVA)Cumberland Borrow Site Access RoadCGPInactiveN/ANashville-27-MAR-201830-SEP-2026
TNR051933Tennessee Valley Authority (TVA)Cumberland Fossil Plant (CUF)TMSPActiveN/ANashville19-JUL-202020-JUL-202030-JUN-2025
NR2104.219Tennessee Valley Authority (TVA)TVA - Cumberland Mooring Cell Repair (Maintenance Activities)ARAPActiveN/ANashville-05-AUG-202107-APR-2025
NR2104.127Tennessee Valley Authority (TVA)Cumberland Projects Minor Water WithdrawalARAPActiveN/ANashville-10-MAY-202107-APR-2025
NR2004.229Tennessee Valley Authority (TVA)TVA - Cumberland Intake Skimmer RepairARAPActiveN/ANashville-22-JAN-202107-APR-2025
NRS17.296Tennessee Valley Authority (TVA)Cumberland Fossil Plant Landfill - Develop 2 Borrow Sites at Wells Creek with Tributaries and WetlandsARAPModificationMajorNashville20-DEC-201820-DEC-201819-DEC-2023
NRS17.221Tennessee Valley Authority (TVA)TVA-Cumberland Fossil Plant Bank StabilizationARAPInactiveN/ANashville27-JUL-201727-JUL-201726-JUL-2020
NRS15.241Tennessee Valley Authority (TVA)Cumberland Fossil Plant - Morring Cell Restoration Project at Barkley LakeARAPInactiveN/ANashville18-AUG-201518-AUG-201506-APR-2020
NRS12.241Tennessee Valley Authority (TVA)Cumberland Fossil Plant Fly Ash and Gypsum Barge Loading Areas Dredging Project and Maintenance Activities at Cumberland RiverARAPInactiveN/ANashville12-MAR-201312-MAR-201311-MAR-2018
NRS11.087Tennessee Valley Authority (TVA)Cumberland City Road Bridge Scour ProtectionARAPInactiveN/ANashville15-APR-201115-APR-201114-APR-2016
NRS13.088Tennessee Valley Authority (TVA)Cumberland Fossil Plant - Bank Stabilization - Fly Ash and Gypsum Barge Loading Areas Dredging Project at Barkley ReservoirARAPInactiveN/ANashville31-MAY-201331-MAY-201330-JUN-2015
NRS11.066Tennessee Valley Authority (TVA)TENNESSEE VALLEY AUTHORITY (TVA) - CUMBERLAND FOSSIL PLANT (CUF) - REPAIR OF EXISTING BUMPER CELL NO. 56ARAPInactiveN/ANashville24-MAR-201124-MAR-201124-MAR-2013
NRS03.232Tennessee Valley Authority (TVA)Cumberland Fossil PlantARAPInactiveMinorNashville09-FEB-200409-FEB-200409-FEB-2009
NRS05.366Tennessee Valley Authority (TVA)-ARAPInactiveN/ANashville20-SEP-200520-SEP-200519-SEP-2008
NRS00.263Tennessee Valley Authority (TVA)-ARAPInactiveMinorNashville18-OCT-2000-18-OCT-2005
  • 1 - 33 of 33

Permit Documents

View
ReportRCVD VIA EMAIL 28-JUN-24: report re: annual seep report by William Patterson28-JUN-2024
LetterThe Division approves TVA’s request to use their existing plans of closing units as it retires their use of coal by 2028 as registered and published in the Federal Register on January 20, 2023.21-JUN-2024
LetterRCVD VIA EMAIL 31-MAY-24: letter re: compliance w/ impingement mortality reduction by Paul Pearman31-MAY-2024
ReportRCVD VIA EMAIL 27-FEB-24: report re: revised biological sampling plan & seep action plan by Paul Pearman27-FEB-2024
Public Notice DocumentRCVD 30-JAN-24: public notice document re: invoice, affidavit and tearsheet from Leaf Chronicle30-JAN-2024
ReportRCVD VIA EMAIL 25-JAN-24: report re: ELG 2023 by William Patterson25-JAN-2024
PermitFinal NPDES Permit 2023 (minor modification 01/03/2024)30-NOV-2023
Public Hearing DocumentREF 16-NOV-23: public hearing document re: attendance sheet by TDEC16-NOV-2023
Public Hearing DocumentREF 16-NOV-23: public hearing document re: hearing recording by TDEC16-NOV-2023
LetterRCVD VIA EMAIL 07-NOV-23: letter re: comments on Draft by Paul Pearman07-NOV-2023
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

no data found

Inspections

31-JUL-2024Compliance Eval (non-sampling) (CEI)Pending
26-MAY-2022Compliance Eval (non-sampling) (CEI)In Compliance
23-SEP-2020Compliance Eval (non-sampling) (CEI)In Compliance
17-JUL-2018Compliance Eval (non-sampling) (CEI)In Compliance
16-SEP-2016Compliance Eval (non-sampling) (CEI)In Compliance
26-AUG-2014Compliance Eval (non-sampling) (CEI)In Compliance
22-MAY-2012Compliance Eval (non-sampling) (CEI)In Compliance
17-JUN-2010Compliance Eval (non-sampling) (CEI)In Compliance
01-NOV-2007Compliance Eval (non-sampling) (CEI)In Compliance
14-MAR-2006Compliance Biomonitoring (CBI)Minor Deficiency Noted

Wastewater Engineering Plans Review

22.0327ApprovedPP-ERTNH7/25/20227/29/2022Cumberland Fossil Plant Process Flow Management Project
21.0390ApprovedCDTNH5/13/20216/2/2021Contaminated Stormwater Basin
20.0645ApprovedCDTNH11/23/202012/1/2020WET FLUE GAS DESULFURIZATION (FGD) WASTEWATER TREATMENT PROJECT
19.0805ApprovedPP-ERVMJ12/19/20193/13/2020TVA Cumberland Fossil Plant Wastewater Treatment Plant
18.0606ApprovedINDVMJ7/20/20188/21/2018CUF Process Water Basin Installation
18.0350ApprovedPERVMJ5/25/20186/12/2018Cumberland Fossil Plant Process Flow Management Project