Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO Name
5107Tullahoma STP1012 S. Franklin StTullahomaCoffeeColumbia

Permit Information

TN0023469
Individual
Reissuance
Tullahoma Utilities Authority
Tullahoma STP
Treatment of municipal sewage using equalization lagoon, sequencing batch reactor, and peracetic acid disinfection
M
M
MW
02-FEB-2022
19-JAN-2022
02-FEB-2022
12-APR-2022
01-AUG-2022
01-SEP-2022
31-JUL-2027
18-FEB-2021
Rock Creek at mile 11.0
treated municipal wastewater from Outfall 001
Equalization lagoon, sequencing batch reactor, and peracetic acid disinfection
4952
5
08-JUL-2024 03:49PM

Other DWR permits at this site

  • 1 - 2 of 2
  • 1 - 2 of 2

Permit Documents

View
Letter24.0119 Approval letter 2024041111-APR-2024
Letter24.0119 Utility Approval letter 2024041111-APR-2024
Inspection Report2024 PCI Feb14-FEB-2024
Form2024 PCI Form Feb14-FEB-2024
Letter2024 WWTP Operator Certifications29-JAN-2024
LetterDW20240029 Approval Letter24-JAN-2024
Letter23.0578 Approval letter 2024010404-JAN-2024
Letter23.0557 Approval letter 2023120812-DEC-2023
Letter23.0518 Approval letter17-OCT-2023
Letter23.0578 Utility Approval letter 06-OCT-2023
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections

07-FEB-2024Pretreatment Compliance (oversight)In Compliance
20-SEP-2023Performance Audit (PAI)In Compliance
18-JAN-2023Pretreatment TAV and File ReviewIn Compliance
26-JAN-2022Pretreatment Compliance (oversight)In Compliance
13-OCT-2021Compliance Sampling (CSI)In Compliance
01-SEP-2021Compliance Eval (non-sampling) (CEI)In Compliance
02-DEC-2020Pretreatment AuditIn Compliance
30-JAN-2020Pretreatment TAV and File ReviewIn Compliance
19-MAR-2019Compliance Biomonitoring (CBI)In Compliance
15-JAN-2019Pretreatment Compliance (oversight)In Compliance

Wastewater Engineering Plans Review

04.1114Approved-A. Bahour9/24/200410/26/2004SETTLERS TRACE
07.0140ApprovedLINEMNU2/7/20072/28/2007Collinwood Court S/D
12.0661ApprovedREHABA. Bahour11/5/201211/20/2012SRF Sanitary Sewer System Rehab and Replacement 2012
14.0238ApprovedREHABPhil Simmo4/30/20146/4/2014SRF - Rehabilitation and Replacement
14.0421ApprovedCDA. Bahour6/23/20147/21/2014Collinwood Court
14.0918ApprovedSTDSPECA. Bahour12/15/20141/13/2015Standard Sewer Specifications
15.0329ApprovedLINEA. Bahour5/28/20156/10/2015Cedar Lane Sewer Line Extension
15.0479ApprovedSTPUPGRJAH8/18/20159/10/2015Blower Replacement Project
15.0502Approved-JAH1/21/20162/1/2016Conversion to Peracetic Acid Disinfection
17.0108ApprovedCDA. Bahour2/15/20172/15/2017Collinwood Court