171237Ridgeline/East Tennessee Gas pipeline projectNear Lewis LaneMontereyPutnamCookevilleView Map

Permit Information

NRS24.014
ARAP
Individual Permit
Pending
When initially received, all applications are identified as "Pending." Pending status indicates that the application is in the que to be processed or that TDEC-DWR staff are reviewing the application (or Notice of Intent for general permits). Status "Pending" could be also interpreted as "work in progress."
East Tennessee Natural Gas, LLC
Ridgeline Expansion Project
The Project consists of the installation of approximately 118 miles of 30-inch diameter pipeline and an approximately 4-mile 30-inch diameter header pipeline (collectively referred to as the Mainline), a 14,600-horsepower (HP) electric-powered compressor station with natural gas backup (Hartsville Compressor Station), an 8-megawatt (MW) solar power generation facility, installation of two new and modification of two existing metering and regulating (M&R) stations, and other appurtenant facilities
N/A
10-DEC-2024
12-AUG-2024
Multiple waterbodies including perennial steams. intermittent streams, and ponds/impoundments
10-DEC-2024 02:05PM

Other DWR permits at this site

No other permits found.

Permit Documents

View
AddendumAttachment 1 - Application Form10-DEC-2024
AddendumAttachment 4 - Concurrence and Correspondence10-DEC-2024
AddendumAttachment 5 - Delineation Reports10-DEC-2024
AddendumAttachment 6 - Mitigation Plan10-DEC-2024
AddendumAttachment 2 - Project Figures10-DEC-2024
AddendumRevised Application10-DEC-2024
AddendumRidgeline Project Design Shapefiles (Zip File)10-DEC-2024
AddendumAttachment 3 - Oversize Tables10-DEC-2024
AddendumAttachment 8 - Environmental Plans 10-DEC-2024
AddendumAuthorized Alternatives10-DEC-2024