City of Celina
Municipal STP
treatment of municipal sewage in a three cell lagoon system
I
M
MW
18-FEB-2020
18-FEB-2020
21-FEB-2020
25-FEB-2020
03-APR-2020
01-MAY-2020
30-APR-2025
Cumberland River at mile 380.7 (Cordell Hull Lake)
treated municipal wastewater from Outfall 001
three cell lagoon system
4952
.8
08-JUL-2024 03:41PM

Other DWR permits at this site

Permit Documents

View
Letterincomplete application ltr TN006388601-OCT-2014
Draft Permitdraft permit 202026-FEB-2020
EmailWDM Response to J. Hamilton regarding submittals for disinfecting change08-SEP-2017
ApplicationUpdated CN-1090 for 2020 Reissue (in conjunction with application received 9/17/18 and schematic in file record dated 9/14/04).18-FEB-2020
Green CardSigned and returned green card28-SEP-2020
Green CardSigned Green card for NOV CRM22-SEP-2022
Green CardSigned Green card 13-APR-2023
Green CardReturned Signed Green CARD 02-AUG-2021
Topo MapREF 24-NOV-03: topo map re: Celina quadrangle by TopoZone.24-NOV-2003
ReportREF 18-FEB-86: report re: proposed WWTP by TDEC.18-FEB-1986
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

OverflowsEFO CommunicationCity of Celina performed a Self Imposed Moratorium due to chronic overflows within the collection system. The City has developed a Corrective Action Plan with James C. Haley and Associates. the City is seeking funding. 3/16/2020Active75

Inspections

05-JAN-2017CSO Inspection Non-SamplingIn Compliance
21-APR-2022Compliance AssistanceIn Compliance
07-APR-2022Compliance AssistanceIn Compliance
20-FEB-2020Compliance AssistanceIn Compliance
02-JUL-2019Compliance AssistanceIn Compliance
03-DEC-2018Compliance AssistanceIn Compliance
14-MAR-2023Compliance Eval (non-sampling) (CEI)Out of Compliance
28-JUL-2022Compliance Eval (non-sampling) (CEI)Out of Compliance
01-DEC-2017Compliance Eval (non-sampling) (CEI)Out of Compliance
22-FEB-2016Compliance Eval (non-sampling) (CEI)Out of Compliance

Wastewater Engineering Plans Review

23.0096ApprovedCDMNU2/21/20233/7/2023Celina CDBG Sanitary Sewer Rehabilitation Project
23.0030Review CompletePPDTNH1/9/2023-Celina Splash Pad
22.0604RApprovedCDMJB10/27/202211/1/20222021 CDBG Sanitary Sewer Rehabilitation Project
22.0604ApprovedCDMJB9/23/202210/11/20222021 CDBG Sanitary Sewer Rehabilitation Project
16.0211ApprovedLINEMNU3/17/20164/6/2016Meadows Lane Project
15.0304ApprovedREHABA. Bahour7/1/20157/1/2015Contract 215
13.0575ApprovedREHABMNU9/5/20139/27/2013Contract 113