Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO Name
5832Monteagle STP, Plant #3Highway 64 WestMonteagleGrundyChattanooga

Permit Information

TN0080985
Individual
Reissuance
Town of Monteagle
Monteagle Sewer Treatment Plant #3
treatment of domestic wastewater with a 0.5 MGD sequencing batch reactor with chlorination
I
M
MW
23-MAR-2022
13-APR-2022
30-AUG-2022
30-SEP-2022
01-OCT-2022
30-SEP-2027
unnamed tributary to Gilliam Creek (001) and an unnamed tributary mile 1.0 to Trussell Creek (002)
treated municipal wastewater
Sequencing batch reactor with post equilization, UV disinfecting, step aeration
4952
.5
08-JUL-2024 03:41PM

Other DWR permits at this site

  • 1 - 7 of 7
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
TNR111878City of MonteagleMonteagle Wastewater Treatment Plant #3CGPInactiveN/AChattanooga-24-MAR-2010-
TNB064815Monteagle STP-BiosolidsInactiveN/AChattanooga---
TN0064815Monteagle STP, Plant #2-IndividualInactiveMinorChattanooga31-MAY-200801-JUL-200831-MAY-2012
TNB080985Monteagle STP, Plant #3-BiosolidsActiveN/AChattanooga14-JUL-201414-JUL-201430-APR-2019
NR1001.001Town of Monteagle-ARAPInactiveN/AChattanooga-12-JAN-201030-JUN-2010
NR1001.002Town of Monteagle-ARAPInactiveN/AChattanooga-12-JAN-201030-JUN-2010
NR1001.003Town of Monteagle-ARAPInactiveN/AChattanooga-11-JAN-201030-JUN-2010
  • 1 - 7 of 7

Permit Documents

View
LetterCompliant Illicit Discharge10-OCT-2013
LetterNotice of Approval of spreading Municiple Bio-solids16-OCT-2013
Monitoring ReportDMR Oct 201319-NOV-2013
ApplicationRCVD 16-DEC-13: NPDES app by Marilyn Campbell.16-DEC-2013
Monitoring ReportMORS 201401-JAN-2014
LetterSENT 13-JAN-14: letter to Marilyn Campbell-Nixon re: NOCA by Paul Higgins.13-JAN-2014
LetterNotification of Overflow Event16-MAY-2014
EmailREF 23-MAY-14: email re: receiving stream impairments by Angela Young.23-MAY-2014
EmailREF 28-MAY-14: email re: Juanita Creek from Mark Barb.28-MAY-2014
Draft PermitTN0080985 Internal Draft Permit for 6/9/2014 PN09-JUN-2014
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

I/I:O & M:Overflows:WWTP OverloadAgreed OrderThe moratorium is no longer active. The order was never finalized and the facility has only reported 1 overflow in the past 2 years. Verified with CH-EFO. (EJM 2-15-2019)1/24/2006Closed58

Inspections

04-JUN-2024Sanitary Sewer SystemIn Compliance
22-JUL-2021Compliance Sampling (CSI)Out of Compliance
19-APR-2017Compliance Eval (non-sampling) (CEI)Out of Compliance
09-JAN-2013Compliance Eval (non-sampling) (CEI)Follow-up Inspection Required

Wastewater Engineering Plans Review

24.0080ApprovedCDTNH2/21/20243/18/20242023 Sanitary Sewer Rehabilitation Project
24.0017Review CompletePERTNH1/5/20241/12/20242023 Sanitary Sewer Rehabilitation Project
15.0398Inactive-PJH6/25/2015-WWTP-Alternative Disinfection Fee
09.0778ApprovedPSFMA. Bahour10/21/200910/28/2009ARRA - Wastewater Treatment Plant and Phases 1 and 2 Collection System Replacement