Site IDSiteLocationCityCountyEFO Name
6397Pegram STP5227 Walkup RoadPegramCheathamNashville

Permit Information

TN0074586
Individual
Incomplete
Town of Pegram
Pegram STP
Septic tanks, collection system, recirculating sand filter with UV disinfection with discharge to Outfall 001 (not installed), and drip irrigation disposal (fenced) to dispose of 0.036 MGD.
I
M
MW, DI
19-JUL-2024
14-AUG-2024
04-AUG-2021
26-OCT-2021
30-NOV-2021
01-JAN-2022
31-DEC-2026
Harpeth River at mile 46.7
treated domestic wastewater from Outfall 001 and drip irrigation of treated wastewater on field below the STP site
STEP collection system, RSF (0.05 MGD); 001 - UV & discharge or 002 - drip irrigation (0.036 MGD) (fenced)
4952
.05
15-AUG-2024 07:21AM

Other DWR permits at this site

No other permits found.

Permit Documents

View
Letter04-SEP-13 CEI letter & 356027-SEP-2013
Inspection Report17-NOV-11 UIC insp17-NOV-2011
Model1996 Streeter Phelps Model19-NOV-2018
Model2001 Streeter Phelps Model05-SEP-2001
Engineering Drawings-Plans2007 As-Built Plans01-MAY-2007
Form2016 Certified Operator Form23-AUG-2016
Inspection Report2018 CEI letter02-JUL-2018
Notice of Violation2022 Pegram CEI NOV02-DEC-2022
Letter21.0811 Approval TDEC letter13-DEC-2021
Letter24.0667 ER-PP Approval LTR 2024090606-SEP-2024
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

no data found

Inspections

03-JUL-2024Compliance Eval (non-sampling) (CEI)Out of Compliance
02-JUL-2024Compliance Eval (non-sampling) (CEI)Out of Compliance
11-JAN-2024Compliance Eval (non-sampling) (CEI)Out of Compliance
18-OCT-2022Compliance Eval (non-sampling) (CEI)Out of Compliance
19-JUN-2018Compliance Eval (non-sampling) (CEI)Immediately Corrected During Inspection
27-OCT-2016Compliance Eval (non-sampling) (CEI)In Compliance
04-SEP-2013Compliance Eval (non-sampling) (CEI)Minor Deficiency Noted
17-NOV-2011Compliance Eval (non-sampling) (CEI)NOV
25-JUN-2009Compliance Eval (non-sampling) (CEI)NOV
24-FEB-2006Compliance Eval (non-sampling) (CEI)NOV

Wastewater Engineering Plans Review

24.0667PendingPP-ERRGO8/26/20249/5/2024Pegram Wastewater Treatment Facility Improvements
24.0554PendingPERRGO7/19/20248/20/2024Pegram Wastewater Treatment Facility Improvements
24.0477Review CompletePPDTNH6/10/2024-Pegram WWTP Improvements
22.0115ApprovedCDA. Bahour8/5/20228/5/2022The Farm at Cedar Valley
21.0811ApprovedCDA. Bahour12/6/202112/13/2021Evergreen Acres
15.0451ApprovedLINEMNU9/16/20159/17/2015Elkins Sewer Line Extension
12.0247InactiveERA. Bahour5/21/2012-SRF Recirculating Sand Filter Drip Field and Process Improvements
98.0102ApprovedRECSFSPW2/3/19984/2/1998RCSF & INTERCEPTOR FM