Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO Name
5861Brookfield Smoky Mountain Hydro, LLC ChilhoweeHighway 129MaryvilleBlountKnoxville

Permit Information

TN0065528
Individual
Revoke_Reissue
Brookfield Smoky Mountain Hydropower LLC
Chilhowee Powerhouse Hydro Plant
Electric Services; Revoke and reissue to align the permit period with the permittee's other hydro plant permitted as NPDES # TN0065510.
I
X
NPW
28-OCT-2022
17-NOV-2022
20-DEC-2022
24-JAN-2023
01-MAY-2023
30-APR-2028
Little Tennessee River at mile 33.6 (Tellico Reservoir)
noncontact cooling water from Outfalls 001, 002 and 003 and nonprocess wastewater from Outfall 004
non-contact cooling water from heat exchangers and generators from Outfalls 001, 002 and 003 and non-process wastewater from Outfall 004
4911
3.04
07-SEP-2023 01:49PM

Other DWR permits at this site

  • 1 - 3 of 3
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
TNR133249Alcoa Power Generating Inc., Tapoco Division-CGPInactiveN/AKnoxville-04-SEP-2008-
TNR134955Brookfield Smoky Mountain Hydro, LLCChilhowee North Embankment Repair - CalderwoodCGPInactiveN/AKnoxville-23-SEP-2016-
NRS16.207Brookfield Smoky Mountain HydropowerChilhowee Dam Repair of the North Embankment at Chilhowee ReservoirARAPInactiveMinorKnoxville20-SEP-201620-SEP-201619-SEP-2021
  • 1 - 3 of 3

Permit Documents

View
Inspection ReportCEI Report 202313-JUN-2023
EmailEmail Correspondence about Missing Samples 18-APR-2023
PermitFinal permit; Issue 1/24/2324-JAN-2023
Draft PermitDraft permit; PN 12/20/2220-DEC-2022
ApplicationRCVD VIA EMAIL 28-OCT-22: NPDES app by Ashley Thomas.28-OCT-2022
Inspection ReportCEI for Chilhowee Hydro07-AUG-2020
Old PermitTN0065528 Final Permit; Issue 9/5/1807-SEP-2018
Draft PermitDraft permit; PN 7/31/1801-AUG-2018
LetterNotice of Complete Application for NPDES Permit Number TN006552819-JUL-2018
ApplicationRCVD VIA EMAIL 09-JUL-18: NPDES app by Marshall Olson.09-JUL-2018
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

no data found

Inspections

07-JUN-2023Compliance Eval (non-sampling) (CEI)In Compliance
07-AUG-2020Compliance Eval (non-sampling) (CEI)In Compliance
18-JUN-2018Compliance Eval (non-sampling) (CEI)In Compliance
30-JUL-2015Compliance Eval (non-sampling) (CEI)In Compliance
26-AUG-2009Compliance Eval (non-sampling) (CEI)In Compliance

Wastewater Engineering Plans Review

no data found