Site IDSiteLocationCityCountyEFO Name
5144South Pittsburg STP725 Willow Ave.South PittsburgMarionChattanooga

Permit Information

TN0024295
Individual
Reissuance
City of South Pittsburg
South Pittsburg STP
Treatment of municipal sewage
M
M
MW
26-NOV-2024
16-DEC-2024
21-APR-2020
01-JUN-2020
01-JUL-2020
30-JUN-2025
Tennessee River Mile 417.3
treated municipal wastewater from Outfall 001
duel activated sludge package units with chlorination
4952
1.5
16-DEC-2024 04:35PM

Other DWR permits at this site

  • 1 - 3 of 3
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
TNR112151City of South Pittsburg(New) South Pittsburg WWTPCGPInactiveN/AChattanooga-23-APR-2012-
TNB024295South Pittsburg STP-BiosolidsActiveN/AChattanooga19-MAY-202119-MAY-202115-AUG-2024
TNRX50146South Pittsburg Wastewater Plant-TMSPNo ExposureN/AChattanooga---
  • 1 - 3 of 3

Permit Documents

View
EmailPT Document Request 07-JAN-2025
ApplicationRCVD 26-NOV-24: cover letter, contact sheet, Form 2A, and maps, by Samantha Rector26-NOV-2024
ReportRCVD VIA EMAIL 22-NOV-24: report re: biomonitoring data from 2024, 2023, 2022, and 2021, from Clark Duggar22-NOV-2024
EmailPT Document Request 18-JUN-2024
EmailPT Document Request Reply Could Not Locate 18-JUN-2024
LetterPT Program Modification Final Approval SUO ERP06-JUN-2024
Public Notice DocumentPT Program Modification Public Notice SUO ERP04-JUN-2024
Monitoring ReportMOR Apr 202401-MAY-2024
LetterPT Program Modification SUO ERP Preliminary Approval25-APR-2024
EmailPT SUO ERP given Preliminary Approval23-APR-2024
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections

18-DEC-2024Compliance Sampling (CSI)Out of Compliance
20-NOV-2023Pretreatment Compliance (oversight)Out of Compliance
03-NOV-2022Pretreatment TAV and File ReviewIn Compliance
16-AUG-2022Compliance Eval (non-sampling) (CEI)In Compliance
27-OCT-2021Pretreatment Compliance (oversight)In Compliance
26-OCT-2021Sanitary Sewer Overflow Non-SamplingIn Compliance
04-MAR-2021Pretreatment AuditIn Compliance
09-DEC-2019Pretreatment TAV and File ReviewIn Compliance
30-SEP-2019Compliance Sampling (CSI)In Compliance
13-DEC-2018Pretreatment Compliance (oversight)In Compliance

Wastewater Engineering Plans Review

24.0726Inactive--9/20/2024--
21.0744Review CompleteCDMJB10/12/202110/28/2021Sewer System Improvements (SRF Project)
20.0399ApprovedCDMJB6/26/20207/23/202015th Street Pump Station and Collection System
13.0734ApprovedLINEMNU12/3/20131/14/2014South Pittsburg FIDP Project Contract II
12.0522Review CompletePERJMS7/26/20128/16/2012CDBG-2012 - South Pittsburg Wastewater Treatment Plant Project
06.0772ApprovedIMPMNU6/20/20061/16/2008Sewer Treatment Plant