Site IDSiteLocationCityCountyEFO Name
5137City of Cookeville Department of Water Quality Control (WWTP)1870 South Jefferson AvenueCookevillePutnamCookeville

Permit Information

TN0024198
Individual
Reissuance
City of Cookeville
Cookeville Municipal POTW
Treatment of municipal sewage
M
M
MW
30-NOV-2021
15-DEC-2021
03-MAY-2022
21-JUN-2022
01-JUL-2022
30-JUN-2027
Pigeon Roost Creek at mile 2.3
Treated municipal wastewater from Outfall 001
Oxidation ditch activated sludge with ultraviolet disinfecting of both treated effluent and storm flow that bypasses the ditch into a standby clarifier.
4952
14
13-DEC-2024 11:25AM

Other DWR permits at this site

Permit Documents

View
Report Oct 2018 PT SAR23-OCT-2018
Report Overflow Report - December 2329-DEC-2014
Report11.24.2021 Overflow Reports24-NOV-2021
Letter15-0777 approval letter with conditions for temporary use of PAA for disinfection during replacement of the UV system29-FEB-2016
Letter15-0777 transmittal cover letter from CTI13-FEB-2020
Letter15-0785 Approval Letter07-JAN-2016
Email15-0785 Project Summary15-DEC-2015
Letter15-0796 Letter07-JAN-2016
Letter15-0796 Ltr08-DEC-2015
Letter15-0848 plans approval19-AUG-2021
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

I/IEFO CommunicationConcerns with I/I2/23/2022Watch List67

Inspections

04-DEC-2023Pretreatment TAV and File ReviewIn Compliance
21-NOV-2023Compliance Eval (non-sampling) (CEI)In Compliance
05-DEC-2022Pretreatment Compliance (oversight)In Compliance
10-DEC-2021Compliance Biomonitoring (CBI)In Compliance
09-DEC-2021Pretreatment TAV and File ReviewIn Compliance
17-DEC-2020Pretreatment Compliance (oversight)In Compliance
31-JAN-2020Compliance Eval (non-sampling) (CEI)In Compliance
09-DEC-2019Pretreatment AuditOut of Compliance
26-NOV-2018Pretreatment TAV and File ReviewIn Compliance
22-JUL-2018Compliance Biomonitoring (CBI)In Compliance

Wastewater Engineering Plans Review

24.0796Pending-RGO10/23/202410/30/2024Redbud Village
24.0137PendingCDRGO2/22/20243/6/2024Morris Hills Subdivision
23.0581PendingCDMJT10/9/202310/23/2023Caliber Collision - Cookeville - Sewer Extension
23.0571PendingCDJKM10/2/20237/29/2024Emerald Forests Subdivision
21.0743RPendingCDA. Bahour8/18/202311/13/2023Ansley Park - Ruby Lane
23.0270PendingCDA. Bahour5/26/20238/4/2023Cookeville CDBG Sewer System Improvements
23.0107PendingCDMNU2/24/20233/27/2023Saxony Townhomes
23.0106PendingCDMJB2/23/20234/18/2023D-251 Brookview Sewer Line
23.0079PendingCDTNH2/15/20233/20/2023Cane Creek Sanitary Sewer System
22.0739PendingCDMNU11/30/20221/9/20232022 South Jefferson CIPP Project