Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO Name
5174Manchester Water and Sewer Department736 West High StreetManchesterCoffeeColumbia

Permit Information

TN0025038
Individual
Reissuance
City of Manchester
Municipal POTW
Treatment of municipal sewage by extended aeration activated sludge (oxidation ditch) and UV disinfecting
M
M
MW
27-JUL-2023
19-JUL-2023
27-JUL-2023
05-DEC-2023
09-FEB-2024
01-MAR-2024
28-FEB-2029
Duck River at mile 268.5
treated municipal wastewater from Outfall 001
Oxidation ditch treatment with chlorine disinfection and dechlorination. Sludge is aerobically digested for land application.
4952
4.3
29-OCT-2024 12:20PM

Other DWR permits at this site

  • 1 - 2 of 2
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
TNB025038Manchester STP-BiosolidsReissuanceN/AColumbia25-JUL-201425-JUL-201430-APR-2019
TNR181153Manchester Water and Sewer DepartmentWastewater Treatment Plant ImprovementsCGPInactiveN/AColumbia-23-NOV-2009-
  • 1 - 2 of 2

Permit Documents

View
Letter24.0799 Plans Approval LTR 2024112525-NOV-2024
Letter2024 Self-Imposed Moratorium Response by Manchester for Manhole B4904-NOV-2024
Letter24.0778 Plans Approval LTR 2024101616-OCT-2024
Letter2024 Self-Imposed Moratorium Manhole B49 Oct02-OCT-2024
LetterWPN23.0608 Approval Letter 2024080808-AUG-2024
Notice of ViolationPT SAR NOV Failure to sample biosolids17-JUN-2024
Email2024 Taps Approved by City14-JUN-2024
Letter2024 Discharge Notification due to Coffee St. & Madison St. Disagreement June14-JUN-2024
EmailEmail regarding Biosolids Sampling13-JUN-2024
Letter2024 Self-Imposed Moratorium for B43 Response June10-JUN-2024
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

I/IPermitorder closed--reverts to permit conditions4/4/2024Watch List75
Chronic OverflowsLetterSelf-imposed moratorium on connections to the wastewater collection system that ultimately flow to Manhole A43.4/30/2024Active
Chronic OverflowsLetterSelf-imposed moratorium on connections to the wastewater collection system that ultimately flow to Manhole B43.5/16/2024Active
Chronic OverflowsLetterSelf-imposed moratorium on connections to the wastewater collection system that ultimately flow to Manhole B49.10/2/2024Active
Chronic OverflowsLetterSelf-imposed moratorium on connections to the wastewater collection system that ultimately flow to Manhole A39.4/30/2024Active
Chronic OverflowsLetterSelf-imposed moratorium on connections to the wastewater collection system that ultimately flow to Manhole I141A.5/7/2024Active

Inspections

29-MAR-2024Performance Audit (PAI)In Compliance
17-MAR-2023Compliance Biomonitoring (CBI)In Compliance
24-FEB-2022Pretreatment TAV and File ReviewIn Compliance
23-FEB-2022Compliance Eval (non-sampling) (CEI)In Compliance
10-MAR-2021Compliance Eval (non-sampling) (CEI)In Compliance
23-FEB-2021Pretreatment Compliance (oversight)In Compliance
27-FEB-2019Compliance Sampling (CSI)In Compliance
27-FEB-2019Pretreatment TAV and File ReviewIn Compliance
07-FEB-2018Performance Audit (PAI)In Compliance
24-JAN-2018Pretreatment Compliance (oversight)In Compliance

Wastewater Engineering Plans Review

09.0774ApprovedSTPUPGRA. Bahour10/20/200910/21/2009ARRA - Wastewater Treatment Plant Upgrade and Expansion
10.0468ApprovedSTDSPECA. Bahour8/12/20108/23/2010Standard Sewer Line Specifications
12.0504Review CompletePERJMS7/26/20128/16/2012CDBG-2012 - Manchester Sewer System Rehabilitation
13.0220ApprovedERPhil Simmo5/2/20135/3/2013FIDP - MDS Foods
13.0249ApprovedPERPhil Simmo5/20/20135/29/2013FIDP - MDS Foods, Inc
13.0655ApprovedPERPhil Simmo10/31/201311/4/2013FIDP - Great Lakes Cheese
13.0686ApprovedLINEMNU11/15/201312/16/2013Great Lakes Cheese Utility Extension Contract
14.0325ApprovedPSFMA. Bahour5/14/20146/24/2014Proposed Hotel - Highway 53
14.0823ApprovedLINEA. Bahour11/5/201412/19/2014Roberts Boulevard Sanitary Sewer Relocation Project
15.0123ApprovedCDMNU2/25/20154/10/2015Northridge S/D, Highway 41