Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO Name
27865Farmington Woods SubdivisionCarver LaneLebanonWilsonNashville

Permit Information

TNR145386
CGP
Inactive
Farmington Woods, LLC
Phases 3, 4, & 5 This project consist of road grading, drainage, and utilities construction for a 42 lot subdivision.
16-MAR-2007
15-MAR-2007
11-APR-2007
14-MAR-2014
Barton's Creek
01-JUN-2023 01:51PM

Other DWR permits at this site

  • 1 - 8 of 8
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
NR2404.152City of Lebanon, Utilities DepartmentFarmington Woods PS RemovalARAPActiveN/ANashville-22-JUL-202407-APR-2025
TNR244595Farmington Woods, LLCFarmington Woods - Phase 10CGPActiveN/ANashville-12-APR-202130-SEP-2026
TNR244279Farmington Woods, LLCFarmington Woods - Phase 4ACGPActiveN/ANashville-27-MAY-202030-SEP-2026
TNR243987Farmington Woods, LLCFarmington Woods - Phase 9ACGPInactiveN/ANashville-19-FEB-202030-SEP-2026
TNR240573Farmington Woods, LLCFarmington Woods - Phases 7, 8, 9CGPInactiveN/ANashville-14-JUN-201630-SEP-2026
TNR149271Farmington Woods, LLCFarmington Woods Subdivision - Phase 6CGPActiveN/ANashville-11-AUG-201430-SEP-2026
NR2004.214Farmington Woods, LLCFarmington Woods - Phase 4A (Intake / Outfall Structure)ARAPActiveN/ANashville-28-AUG-202007-APR-2025
NR2404.190Water Management Svcs.Wetland CrossingARAPIncompleteN/ANashville---
  • 1 - 8 of 8

Permit Documents

There are no electronic documents available for publication on the DataViewer for the selected permit record.

Please contact our staff at Water.Permits@tn.gov for further information.

Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections

no data found

CGP - Specific Information

Area Disturbed (acres)
31.21
Start Date
4/1/2007
Estimated End Date
9/1/2007
Streams
-
Wetlands
-
Exceptional TN Waters (ETW)
No
ETW Comment
-
Threatened and Endangered Species 1 mile radius
No
Threatened and Endangered Species 5 miles downstream
No
Unavailable Conditions Waters
Yes
Unavailable Conditions Waters Comment
-
EPSC Plan Findings
-

Contractors

Contractor 1
Hayes Land Development
Start Date
-
Contractor 2
-
Start Date
-
Contractor 3
-
Start Date
-
Contractor 4
-
Start Date
-
Contractor 5
-
Start Date
-
Contractor 6
-
Start Date
-