4968TVA Allen Fossil Plant D4 Plant Retirement/ Decommissioning and Plant Site Restoration2574 Plant RdMemphisShelbyMemphis

Permit Information

TN0082228
Const-Individual
New
Tennessee Valley Authority (TVA)
Allen Fossil Plant - Final Closure of Ash Ponds
Soil disturbance during removal of the existing Coal Combustion Residual (CCR) and wash water precipitates materials from East and West Ash Ponds. All CCR contact stormwater will be routed through the Water Treatment System during construction.
I
R
SW
03-DEC-2019
01-JAN-2020
14-APR-2020
26-MAY-2020
01-JUN-2020
31-MAY-2025
McKellar Lake, Horn Lake Cut-Off, Mississippi River
stormwater runoff associated with construction activities from outfalls SW1-SW8
construction SW associated with CCR will be all routed through onsite Water Treatment System; otherwise, a site of structural and non-structural EPSC measures will be implemented
4911
17-JUN-2024 10:41AM

Other DWR permits at this site

  • 1 - 25 of 25
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
TNR191856Tennessee Valley Authority (TVA)East and West Ash Pond ClosuresCGPInactiveN/AMemphis-05-DEC-2019-
TNR191760Tennessee Valley Authority (TVA)Allen Fossil Plant Storm Water ReroutesCGPInactiveN/AMemphis-09-OCT-2018-
TNR191746Tennessee Valley Authority (TVA)Allen Fossil Plant Reclamation of Unused Coal and ResidualsCGPInactiveN/AMemphis-28-AUG-2018-
TNR191567Tennessee Valley Authority (TVA)Allen Fossil Plant 161 kV Switchyard ExpansionCGPInactiveN/AMemphis-26-JUL-2016-
TNR191547Tennessee Valley Authority (TVA)Allen Fossil Plant West Ash Pond Final ClosureCGPInactiveN/AMemphis-06-JUL-2016-
TNR192155Tennessee Valley Authority (TVA)TVA Allen Fossil Plant D4 Decommissioning and Site RestorationCGPActiveN/AMemphis-01-OCT-202430-SEP-2026
TNR192266Tennessee Valley Authority (TVA)ACT D4 Demolition and Site RestorationCGPInactiveN/AMemphis-12-MAR-202430-SEP-2026
TNR191994Tennessee Valley Authority (TVA)Allen Fossil Plant Interim Response ActionCGPActiveN/AMemphis-01-JUL-202030-SEP-2026
TNR053184Tennessee Valley Authority (TVA)Allen Fossil PlantTMSPActiveN/AMemphis19-JUL-202020-JUL-202030-JUN-2025
NRS22.130Tennessee Valley Authority (TVA)West Ash Pond Stormwater Outfalls ConstructionARAPActiveN/AMemphis-22-JUN-202207-APR-2025
NRS20.012Tennessee Valley Authority (TVA)West Ash Pond Storm Water Outfalls ConstructionARAPInactiveN/AMemphis-12-FEB-202006-APR-2021
NRS16.258Tennessee Valley Authority (TVA)TVA-Allen Fossil Plant Levee Seep Repair - Installation of 300 ft of Graded Filter at McKellar LakeARAPInactiveN/AMemphis09-DEC-201609-DEC-201606-APR-2020
NRS16.169Tennessee Valley Authority (TVA)Allen Fossil Plant - West Ash Pond Closure - Construction of Stormwater Outfall at McKellar LakeARAPInactiveN/AMemphis11-AUG-201611-AUG-201606-APR-2020
NRS15.216Tennessee Valley Authority (TVA)TVA Allen Fossil Plant - Barge Mooring Cell Restoration at McKellar LakeARAPInactiveN/AMemphis18-AUG-201518-AUG-201506-APR-2020
NRS12.142Tennessee Valley Authority (TVA)Allen Fossil Plan - Recovery of Coal from McKellar LakeARAPInactiveN/AMemphis16-JUL-201216-JUL-201215-JUL-2017
NRS14.235Tennessee Valley Authority (TVA)TVA Allen Fossil Fuel Plant - Bank Stabilization of McKellar LakeARAPInactiveMajorMemphis19-SEP-201419-SEP-201430-JUN-2015
NRS11.179Tennessee Valley Authority (TVA)Allen Fossil Plant - Restoring Mooring CellsARAPInactiveN/AMemphis10-AUG-201110-AUG-201109-AUG-2014
NR1205.011Tennessee Valley Authority (TVA)-ARAPInactiveN/AMemphis14-MAR-201214-MAR-201213-MAR-2014
NRS10.128Tennessee Valley Authority (TVA)-ARAPInactiveN/AMemphis10-JUN-201010-JUN-201009-JUN-2013
NRS09.238Tennessee Valley Authority (TVA)Allen Fossil PlantARAPInactiveN/AMemphis18-AUG-200918-AUG-200917-AUG-2012
NRS05.305Tennessee Valley Authority (TVA)Allen Fossil PlantARAPInactiveMinorMemphis05-JAN-200604-JAN-200604-JAN-2011
TN0005355Tennessee Valley Authority (TVA)Allen Fossil Plant (ALF)IndividualReissuanceMajorMemphis30-NOV-200701-JAN-200803-AUG-2010
TNR190557Tennessee Valley Authority (TVA)Allen Fossil PlantCGPInactiveN/AMemphis-14-OCT-200530-MAY-2010
NR0705.045Tennessee Valley Authority (TVA)-ARAPInactiveN/AMemphis14-JUN-200714-JUN-200713-JUN-2009
NRS07.061Tennessee Valley Authority (TVA)Allen Fossil PlantARAPInactiveN/AMemphis19-MAR-200719-MAR-200731-OCT-2008
  • 1 - 25 of 25

Permit Documents

View
ApplicationApplication for Individual Construction NPDES permit03-DEC-2019
Draft PermitDraft Individual NPDES Permit 202014-APR-2020
EmailTVA comments on Draft NPDES Permit: some outfalls are duplicated and do not have to be in the final permit12-MAY-2020
PermitFinal NPDES Individual construction permit 202026-MAY-2020
ReportTN0082228 TVA April 2021 monthly summary22-JUL-2021
ReportTN0082228 TVA monthly summary May 202122-JUL-2021
EmailEmail regarding status of project as of 7-27-2127-JUL-2021
ReportTN0082228 TVA monthly summary June 202128-JUL-2021
ReportTN0082228 TVA July 2021 Monthly Summary06-AUG-2021
ReportTN0082228 TVA August 2021 Monthly Summary15-SEP-2021